2.
Secure the rail lock brackets to the rack on each side of the unit using either a rack manufacturer-provided
screw or one #10-32 and one #8-32 screw provided with the kit per side.
The #8-32 screw goes through the bottom hole on the bracket, and the #10-32 screw goes through the
top hole.
Use 6 to 7 inch-pounds (0.7 to 0.8 Newton-meters) of torque on these screws.
About grounding the platform
You should ground the platform after you install it in a rack. The chassis ground lug is located on the back
of the platform.
Do not secure multiple bonding or grounding connectors with the same bolt. The grounding connectors do
not need to be removed to perform service or installation procedures. You can connect other bonding or
grounding conductors to a grounding connector provided a reliable bond between the connector and the
equipment is not disturbed during installation, service, or maintenance of the platform.
28
Platform Installation
Содержание 8900
Страница 1: ...Platform Guide 8900 MAN 0330 03 ...
Страница 2: ......
Страница 6: ...6 Table of Contents ...
Страница 23: ...3 Open the hostconsh shell hostconsh 4 Open the AOM Command Menu Esc 23 Platform Guide 8900 ...
Страница 24: ......
Страница 32: ......
Страница 44: ......
Страница 48: ......
Страница 54: ......
Страница 56: ......
Страница 60: ......