8.0 M a inten a n c e
8.3.3 Check of visual condition
To be performed by qualified personnel
1. Separate the actuator from the energy supply.
2. Check the following structural components for visible ex-
ternal damage:
1
2
3
Fig. 9
3. Notify processor or Ewellix in case of damage
4. If there is no damage and the processors/manufacturer
has not communicated any concerns, reconnect the ac-
tuator to the power supply.
8.4 Measures after
completed maintenance
Upon completion of the maintenance, the following steps
have to be performed prior to restarting the device.
1. Ensure that all tools, material and other equipment used
during maintenance have been removed from the work
area.
2. Clean work area and remove potential spills such as liq-
uids, processing material or similar material.
3. Ensure that all safety measures of the system work prop-
erly without a problem.
4. Check to be sure that all actuator and system functions
are operating correctly.
5. Document the maintenance in the service log.
1. Check connecting cables for cracks, cuts and
pinched sections
2. Check hinge hole for cracks, deformation and
broken pieces
3. Check stainless steel tube for scratches and in-
dentations