Exhaust  Venting  Installation

This water heater must be properly vented for removal

of exhaust gases to the outside atmosphere. Correct

installation of the vent pipe system is mandatory for

the safe and efficient operation of this water heater and

is an important factor in the life of the unit.
Vent pipe installation must be performed in accordance

with state and local codes, or in the absence of such,

the latest edition of National Fuel Gas Code, NFPA 54/

ANSI 223.1. Canadian installations must be performed

in accordance with CAN/CGA-B149.

VENT PIPE  MATERIAL

Eternal Hybrid Water Heater is a gas burning appliance

with fan-assisted exhaust. The appliance must be vented

with 4" Category III special venting, which is air tight to

prevent leakage of exhaust gases.
The appliance must be vented separaely from all other

appliances. The following type of non-metallic vent can

be used:

Sealant (silicon based) is recommended with metallic

venting to ensure proper seal.

VENT  PIPE  INSTALLATION

The following guidelines should be followed when in-

stalling the exhaust outlet piping:

The exhaust outlet piping and termination may be in-

stalled in one of the following terminations:
1. Standard Horizontal (see page 22)
2. Vertical (see page 22)
All pipe, fitting, pipe cement, primers and procedure

must conform to American National Standard Institute

and American Society for Testing and Materials (ANSI/

ASTM) standards in the United States.

This water heater has been design certified by CSA In-

ternational for use with the specified listed plastic vent

pipe.

CUTTING  OPENING  THROUGH AN  OUTSIDE  WALL

AND  TERMINATOR  INSTALLATION

The 4" PVC, ABS or CPVC Schedule 40 vent pipe can

be run from the water heater through the wall or from the

wall to the water heater, whichever is most convenient.
The vent pipe must extend a minimum of 1.5" through

the exterior wall. Note that inside collars must be slipped

over the vent piping before locating the pipe through the

wall.
Before securing the inside and outside collars to the

wall, use a silicone sealer between pipe and opening to

ensure water and air tight seal.
To prevent condensate from collecting in the venting sys-

tem slope the vent at a downward pitch of 1/4" per 12 ft.

with condensate trap.

PVC (schedule 40, ASTM-D1785)
PVC-DWV (ANSI/ASTM-D2665)
CPVC (schedule 40, ASTM-D2846)
ABS (schedule 40, ASTM-D2661)

CEMENTING  PVC,  ABS  or  CPVC  PIPE  and  FIT-

TING

All primers, cleaners and cements must meet all local

codes and applicable standards of the American Society

for Testing Materials.
Before using primers, cleaners and cements, stir or

shake, making sure contents are liquid. Do not use if

found to be lumpy or jelly-like.

Cut pipe ends squarely removing all burrs and dirt.
Dry fit pipe and fittings to be connected for proper fit.
Clean pipe and fitting with a primer/cleaner.
Apply a thin coat of cement to fitting, avoiding pud-

ding inside.
Apply a liberal coat of cement to pipe leaving no voids.
Quickly assemble parts while cement is fluid.
Push pipe completely into socket of fitting, turning as

it goes until it bottoms.
Hold pipe and fitting together for 30 seconds. Then

carefully clean off excess with a cloth. Allow connec-

tions sufficient time to cure before disturbing.
Remember that vent pipes must be adequately and

securely supported.

NOTICE

!

For installations in Canada,field supplied plastic vent
piping must comply with CAN/CGA B149 1(latest
edition)and be certified to the Standard For Type
BH Gas Venting Systems,ULC S636 Components
of this listed system shall not be interchanged with
other vent systems or unlisted pipe/fittings. All plastic
components and specified primers and glues of the
certified vent system must be from a single system
manufacturer and not intermixed with other system
manfacturer's vent system parts.
The supplied vent connector and vent termination
are certified as part of the water heater.

!

Venting should be as direct as possible with a mini-

mum number of pipe fittings.
Venting diameter must not be reduced unless spe-

cially noted in the installation instructions.
Support all horizontal pipe runs every four feet ac-

cording to local codes.
Vents run through unconditioned spaces where be-

low freezing temperatures are expected should be

properly insulated to prevent freezing. For horizontal

runs, wrap the vent pipe with self-regulating 3 or 5

watt heat tape. The heat tape must be U.L. listed

and installed per the manufacturer's instructions.
Do not connect this venting system with an existing

vent or chimney.
Do not connect common vent with the vent pipe of

any other water heater or appliance.

_

_

_

_

_

_

1.
2.
3.
4.

5.

6.

8.

9.

7.

Note : Do not use cellular foam core pipe.

Содержание GU20DV

Страница 1: ...l or components of the product itself WARNING WHAT TO DO IF YOU SMELL GAS Do not try to light any appliance Do not touch any electrical switch do not use any phone in your building Immediately call yo...

Страница 2: ...34 Hot water temperature over 125 F can cause severe burns instantly or death from scalding Children disabled and elderly are at the highest risk of being scalded Temperature limiting valves are avai...

Страница 3: ...ce of leaking gas Be sure to smell next to the floor because gas is heavier than air and will settle on the floor B A Installation Codes The installation must conform with local codes or in the absenc...

Страница 4: ...4 Parts Diagrams for Model GU28 32DV 505 11 12 1 28 32 1...

Страница 5: ...006 1 7 Panel Bottom 151010009 1 8 Control Panel Assembly 301080170 1 9 Temperature and Pressure Relief Valve 194010281 1 10 Intake Collar Assembly 307060517 1 11 Top Packing 151010200 1 12 Plug 60102...

Страница 6: ...Parts Diagrams for Model GU20 26DV 505 11 12 1 20 26 1 6...

Страница 7: ...006 1 7 Panel Bottom 151010009 1 8 Control Panel Assembly 301080170 1 9 Temperature and Pressure Relief Valve 194010281 1 10 Intake Collar Assembly 307060517 1 11 Top Packing 151010200 1 12 Plug 60102...

Страница 8: ...faucet Allow water to run until a constant flow is obtained This will let air out of the water heater and piping Open a hot water tap to check that water will flow to that tap Then close the hot wate...

Страница 9: ...mperature Setting Button with unit ON Temperature setting is only adjustable when the water heater is not in use The maximum water temperature setting can be limited by DIP switches This manual settin...

Страница 10: ...ent in faucet aerators shower heads and screens could impair water flow and cause the water heater to deliver less than its full output or to shut down completely Check any of these screens or shower...

Страница 11: ...open A secondary air hole thermistor short open A vent condition is not normal Temperature too high on a burner thermistor Mixing control valve is not connected Mixing control valve initialization fai...

Страница 12: ...Manifold Pressure Gas Valve Type Unit Dimensions WxHxD Electrical Power Supply Unit Weight lbs Gas Input Gas Supply Pressure Combustion Analysis Temperature Settings Thermal Efficiency Packaged Weigh...

Страница 13: ...gas vent The appliance should be located in an area where leakage of the tank or connections will not result in damage to the area adjacent to the appliance or to lower floors of the structure When s...

Страница 14: ...1 Intake Top x 1 O Ring G95 x 1 Exhaust Collar x 1 Valve Adaptor x 1 Orifice for LPG x 1 LPG Label x 1 Top Packing x 1 Drain Cap x 1 Mesh Screen x 2 Self Tapping Screw T4x16 x 5 Philips Head Screw M4...

Страница 15: ...alve on the side of unit Make sure the T P Relief is secured to prevent water leak Please install theTop Packing when using PVC ABS CPVC as the intake pipe Metal pipes such as stain less steel do not...

Страница 16: ...unit on a water heater stand that raises the unit at least 6 from the floor where seepage can accumulate underneath the unit Description In compliance with NSF 5 standard water heaters should be moun...

Страница 17: ...nstalled in a manner which allows inspection of the installation of the venting pipes and joints as well as periodic in spection after installation as required by ANSI Standard When determining the in...

Страница 18: ...least 6 from adjacent unprotected com bustible surfaces Joint of vent connectors should be securely fastened by sheet metal screws or other ap provedmethod The entire vent system must not exceed the s...

Страница 19: ...All vertical terminating vent installations Horizontal terminating vent Installations if a vertical rise in the vent system exceeds 5 ft If more than one elbow is used in the vertical section a conden...

Страница 20: ...ate trap PVC schedule 40 ASTM D1785 PVC DWV ANSI ASTM D2665 CPVC schedule 40 ASTM D2846 ABS schedule 40 ASTM D2661 CEMENTING PVC ABS or CPVC PIPE and FIT TING All primers cleaners and cements must mee...

Страница 21: ...the center line of the terminal E 12 inch min clearance to unventilated soffit F Clearance to outside corner G 2 feet clearance to inside corner formed by two exterior walls H 4 feet clearance to eac...

Страница 22: ...can be vented straight up and horizontal section is not required for vertical terminations Condensate drain must be used in all vertical terminations Venting Material PVC DWV ANSI ASTM D2665 Once the...

Страница 23: ...he unit Remove the gas supply pressure test port screw and connect manometer to this port turn on the gas to the water heater Turn the water heater on and open multiple taps to force unit into high fi...

Страница 24: ...ter heater must be vented in accordance with Venting of Equipment section of the latest edition of the National Fuel Gas Code ANSI Z223 1 and all appli cable local building codes Always use approved c...

Страница 25: ...e must be provided to control thermal expansion Troubleshooting Thermal Expansion Contact the water supplier or local plumbing inspector on how to control this situation WARNING Be careful not to reve...

Страница 26: ...e that 1 For Installations in the State of California Close the water heater drain valve by turning the knob to the right The drain valve is on the lower front of the water heater Open the cold water...

Страница 27: ...st be electrically grounded Label all wires prior to disconnection when servicing controls Wiring error can cause im proper and dangerous operation Verify proper operation after servicing CAUTION Thew...

Страница 28: ...32DV switch 5 OFF switch 4 Test selection switch 2 switch 3 Temperature selection 1 switch 2 Temperature selection 2 switch 1 Temperature selection 3 O N 8 7 6 5 4 3 2 1 switch 8 Reserved switch 7 Res...

Страница 29: ...29 Wiring and Connection Diagram...

Страница 30: ...n 2 screws securing the Control Panel Assembly to the frame and remove the Assembly from Water Heater Loosen 2 screw and the nut of the gas pipe and insert with Orifice LP Tighten the loose nut to mak...

Страница 31: ...Valve Adaptor LP Reverse the steps above by reassembling the packing Gas Flange and Connector Bracket Make sure all screws and secure and tightened Change Dip Switch No 8 position from left to right 8...

Страница 32: ...tion System with an Eternal Water Heater Single Eternal with Storage Back up These diagrams are for reference as basic guides Each installation should be engineered properly and compliant to Local and...

Страница 33: ...ternal with pre heater i e Solar 33 Recirculation with 2 Units manifold These diagrams are for reference as basic guides Each installation should be engineered properly and compliant to Local and Stat...

Страница 34: ...esponsible for shipping charges of such replacement parts This Warranty does not cover any failures or operating difficulties due to accident abuse misuse alteration misapplication vandalism improper...

Отзывы: