PE-K installation 35 to 90 kW
2012-02
Installation
Flue gas recirculation
Remove bottom insulation,
insert connection pipe
Using the round notches in the frame as a guide,
remove the bottom insulation with a knife.
Push bottom insulation under boiler
Install flue gas duct
Insert the seal between the flue gas duct and the
connection pipe.
Attach the flue gas duct with 4 M5 x 20 screws and
tighten them evenly.
Position the flue gas duct on the boiler. Insert the
threaded rod (with spring) on the air box into the
hole on the flue gas duct. Fasten the flue gas duct
to the boiler with 3 M5 x 20 screws.
Attach both covers with seal to the flue gas duct
with M5 countersunk screws.
Remove insulation
Connection pipe
Seal
M5 x 20
Flue gas duct
Attach covers and seal with
M5 countersunk screws
Flue gas recirculation
Содержание PE-K 35
Страница 1: ...PE K pellet boiler 35 to 90 kW Installation PE K installation 35 to 90 kW 2012 02 2012 02 18 EN...
Страница 17: ...17 PE K installation 35 to 90 kW 2012 02...
Страница 25: ...25 PE K installation 35 to 90 kW 2012 02...
Страница 37: ...37 PE K installation 35 to 90 kW 2012 02...
Страница 56: ...56 www eta co at Subject to change due to technical improvements...
Страница 57: ...57 PE K installation 35 to 90 kW 2012 02...
Страница 58: ...58 www eta co at Subject to change due to technical improvements...
Страница 59: ...59 PE K installation 35 to 90 kW 2012 02...