Installing the piping
Connect the piping of the heat producer on the primary
side and the piping for the heat consumer on the
secondary side.
There is a bleed screw on the top area of the heat
transfer station for bleeding the primary side.
Fig. 4-12: Bleed valve for the primary side
A connection for a membrane expansion vessel is
available for the secondary side.
Fig. 4-13: Connection for membrane expansion vessel
For frost protection in the secondary circuit, guide
the safety valve outlet into a canister
DANGER!
Safety valve outlet
The safety valve outlet must be directed to a canister
with sufficient dimensions in a pipe so nobody is
endangered by hot water or steam.
The safety valve outlet must be directed into the
canister via a clearly visible, open route (siphon
funnel) so that malfunctions, especially a failure of
the safety valve to close, can be detected. In the
same way, the frost protection is collected when
opening the safety valve and can be filled again.