7.0 Connecting the service & commissioning touchscreen interface
7.1 Initial boiler start up, bleeding the fuel pump and commissioning
Step 2
- Upon successful loading, the “
Temperature Display
Screen”
will be displayed.
Fig. 10
Press the
“EOGB Logo”
in the top left hand corner to open the “
System Ramp Test
Screen”
.
Any attempt to fire or commission this appliance by
unauthorized persons will invalidate the appliance
warranty.
WARNING
When commissioning or servicing the boiler, the Touchscreen Interface (TSI) MUST be connected in order to make boiler/
burner adjustments. This TSI CAN ONLY be acquired and used by a Sapphire Approved Agent.
To connect the TSI, you must first disconnect the LCD Display on the boilers front panel.
(FIG 7)
. Once disconnected, simply
plug in the TSI
Step 3
- On the “
System Ramp Test Screen”
Fig. 11,
press
the
“Next”
button in the bottom right hand corner to move
through the different setting windows until you reach the
“Run Time System Control Screen”
Fig. 11 - 18
On/Off Switch
Step 1
- Switch on any isolation switches and turn on the
on/off power switch on the boiler front panel.
Fig. 8
Upon initial start up the
“System Loading Screen”
will ap-
pear for several seconds whilst the burner initiates the start
up program.
Fig. 9
Fig. 7
Fig. 11
Fig. 10
Fig. 9
Fig. 8
Boiler Operation and Commissioning
Touchscreen
Interface Port