CATHEDRAL CEILING INSTALLATION 

 
STEP 1. 

Follow installation steps 1 and 2 under Vertical Termination. 

 

STEP 2.

 Using the plumb bob, mark the centerline of the venting system on the ceiling and drill a small hole through the ceiling 

and roof at this point. From the roof, locate the drill hole and mark the outline of the “Cathedral Ceiling Support Box”. 

 

STEP 3.

 Remove shingles or other roof coverings as necessary to cut the rectangular hole for the “Support Box”. Cut the hole 

1/8” larger than the “Support Box” outline. 

 

STEP 4.

 Lower the “Support Box” through the hole in the roof until the bottom of the “Support Box” protrudes at least 2-inches 

below the ceiling.(FIG-20), align the “Support Box“ both vertically and horizontally with a level. Temporarily tack the 
“Support Box” in the place through the inside walls and into the roof sheathing. 

 

STEP 5.

 Using tin snips, cut the “Support Box” from the top corners down to the roofline, and fold the resulting flaps over the 

roof sheathing.(FIG-21). Before nailing it in to the roof, run a bead of non-hardening mastic around the top edges of 
the “Support Box”, to make a seal between the box and the roof. Clean out any combustible material from the inside 
of the “Support Box”. 

 

STEP 6.

 Complete the cathedral ceiling installation by following the same procedures outlined in Steps 4 through 9 for “Vertical 

Termination”. 

 

SHERWOOD INDUSTRIES LTD VENTING KITS 

 
 
Inspect this kit to ensure this kit is complete and there is no damage to any of the components. If damage is present contact 
your dealer or your courier company. If some components are missing or damaged do not attempt the installation. 
 
Decide on a location for the unit that will meet any or all, local code requirements. Refer to sections in this manual. Deciding 
Were To Locate Your Stove, and Planning Your Installation. 
 
Set the appliance in the desired location. Check to determine if any wall studs, electrical wiring or plumbing pipes are in the 
way of the venting system as it passes through the wall. If obstructions are found in the wall it may be required to adjust the 
location of the appliance. 
 
Set the appliance in the desired location. Temporarily place the 24” section 
of pipe (without the crimped end) on the unit and install the 90° elbow 
pointing in the direction that the vent will exit the structure. Project a level 
line from the center point of the elbow. Using this center point, scribe a 10” 
hole or square on the wall. Cut the hole out on both the interior and exterior 
wall surfaces. Install the wall thimble and secure this thimble on both the 
inner and outer wall surfaces. 
With the appliance still in place install the 24” horizontal section on the 
elbow and let this section of pipe protrude through the exterior wall. Mark 
this pipe so that it is flush with the exterior surface and cut this section of 
pipe. 
 
Dismantle the outer pipe sections. 
 
Remove the 4” flue collar from the unit and remove any lose sealant, install 
the new 4” diameter x 5” high flue collar provided in this kit. 
 
Attach the flexible liner to the vent termination cap by placing a small bead 
of high temperature silicone on the vent terminal and slide the flex liner 
onto the vent terminal and secure with 3 sheet metal screws evenly 
spaced. 
Dress the flex liner through the wall thimble and attach the vent terminal to 
the outside of the house using 4 wood screws provided. (The use of non-
hardening mastic should be used around the vent to ensure a watertight seal.)  
 
 
 
 

 

11

Содержание EG-40

Страница 1: ...on may result causing property damage personal injury or loss of life installation and service must be performed by a qualified installer service agency or the gas supplier Do not store or use gasolin...

Страница 2: ...tallation must conform to local codes or in the absence of local codes with the current CAN1 B 149 installation code in Canada or the current National Fuel Gas Code ANSI Z223 1 in the USA To prevent i...

Страница 3: ...IGH ALTITUDE SPECS ENVIRO EG 40 DIRECT VENT UNITS Have all been certified for use with either natural or propane gases See control panel and rating label Are not for use with solid fuels Must not be c...

Страница 4: ...aintenance Locate a position where the flue system of the stove can be properly installed without damaging the integrity of the building E g cutting a wall or ceiling joist The stove can be installed...

Страница 5: ...inimum K Clearance to a mechanical air supply inlet 6 feet 1 8m minimum L Clearance above paved side walk or paved driveway located on public property 7 feet 2 1m minimum M Clearance under verandah po...

Страница 6: ...PERMITTED TO REACH THE OUTSIDE VENT TERMINATION BEFORE BEGINNING THE INSTALLATION TAKE CARE TO ENSURE AN APPROPRIATE OUTSIDE LOCATION FOR THE VENT TERMINATION CAN BE ACCOMMODATED FOLLOW THE VENT LENG...

Страница 7: ...dentations located on the female end of the pipes and fittings are designed to slide straight onto the male ends of adjacent pipes and fittings by orienting the four pipe indentations so they match an...

Страница 8: ...nts excessive heat from possibly melting the vinyl siding material Note that the horizontal vent termination bolts onto the flat portion of the vinyl siding standoff Shaded area in FIG 12 so that an a...

Страница 9: ...pipe and elbows may be utilized in the attic as well as above the roofline The galvanized finish is desirable above the roofline due to the higher corrosion resistance STEP 6 Once the pipe sections h...

Страница 10: ...t the second floor and any subsequent floors FIG 19 The opening should be framed to 10 inch x 10 inch inside dimensions in the same manner as shown in FIG 16 2 Any occupied areas above the first floor...

Страница 11: ...ide on a location for the unit that will meet any or all local code requirements Refer to sections in this manual Deciding Were To Locate Your Stove and Planning Your Installation Set the appliance in...

Страница 12: ...liner over collar secure the flex liner with 3 sheet metal screws evenly spaced Align all straight sections of pipe slipping all joints together and installing 3 sheet metal screws evenly spaced A sm...

Страница 13: ...nimum 4 flex liner to the top of the CLASS A chimney Placing a bead of high temperature silicone to the Simpson Cap adapter and securely attach the flex liner to the adapter Secure the cap adapter to...

Страница 14: ...t is very important to install these logs in their correct position to insure safe optimum operating conditions Open the door of the fireplace Place the logs on the log supports Close the door and tig...

Страница 15: ...f all electrical power to the appliance 3 Turn the gas control knob clockwise to the off position 4 Open door Wait five 5 minutes to clear out any gas Close door If you smell gas including near the fl...

Страница 16: ...first 4 hours of use See page 14 After that depending upon the amount of use cleaning should be required no more than two or three times per season To clean the door use a mild glass cleaner and a so...

Страница 17: ...d Bleed line Check gas line pressure Contact dealer Burners will not remain lit Problem with thermopile circuit Check gas line pressure Check for flame impingement on thermopile if low see Pilot will...

Страница 18: ...the current edition of the National Fuel Gas Code ANSI Z223 1 UPON CONNECTION MARK APPROPRIATE FUEL TYPE ON WARNOCK HERSEY RATING LABEL LOCATED ON THE INSIDE OF THE RIGHT HAND SIDE PANEL Manifold Pres...

Страница 19: ...ly to the floor WARNING ELECTRICAL GROUNDING INSTRUCTIONS This appliance is equipped with a three prong grounding plug for your protection against shock hazard and should be plugged into a properly gr...

Страница 20: ...Voltage Thermostat REMOVING THE BLOWER 20 1 Turn the unit off and remove the log set 2 Remove the burner tray assembly by removing the screw on either side of the tray between the front and rear burne...

Страница 21: ...lot orifice First remove the two 2 T 20 Torx screws that hold the pilot assembly to the burner tray Lift the pilot assembly from the burner tray Using a 10mm wrench disconnect the pilot line from the...

Страница 22: ...ts only thereafter The paint on the Metal Brick Liner may peel This is due to the extreme conditions applied to the paint and is no way covered under warranty Your dealer shall make all claims under t...

Страница 23: ...g Harness Complete 2 pieces 30 014 Freestanding Burner Control NG Complete EC 040 Freestanding Fan Control Knob 30 015 Freestanding Burner Control LP Complete EC 043 IEC Power Cord 30 017 Rear Burner...

Страница 24: ...r 2003 EG40 GAS TRAY AND DOOR ASSEMBLIES Rear Venturi EG40 099 S I T Nova 820 Valve EC 006 NG EC 007 LPG S I T Piezo Ignitor EC 023 Burner Switch EC 025 Light Switch EC 066 FS Fan Controller EF 045 FS...

Страница 25: ...ing Side Panel Cabinet EG40 086 Flue Pipe Freestanding Pedestal Wiring Plate Freestanding Pedestal Box Cover EG40 307 1x1 Side Cabinet Hinge EC 054 Freestanding Side Panel Cabinet EG40 086 Convection...

Страница 26: ..._________ Name of Installer ___________________________________________ Address _______________________________________ ___________________________________________ ____________________________________...

Отзывы: