13
C048-741-30 R01, Rev. B (01/2020)
4.5
4.5 Output Connections
Output Connections
DO NOT PERFORM THIS STEP ON CIRCUITS WITH
BREAKERS OR FUSES INSTALLED. ENSURE NO
POWER IS PRESENT ON THE CIRCUIT BEING WIRED
BEFORE PROCEEDING. MAKE SURE THAT ALL
CABLES HAVE INSULATED TERMINALS OR HEAT
SHRINK APPLIED PRIOR TO TERMINATION, AND THAT
NO-OXIDE COMPOUND IS APPLIED TO ALL COPPER-
TO-COPPER CONNECTIONS.
CAUTION!
Table 3.
Output Specifications
TERMINATION
TYPE
HOLE/
STUD
SIZE
CENTER-
TO-CENTER
RECOMMENDED
TORQUE VALUE
Threaded Stud
1/4-20
5/8 in.
100 in·lbs
Each panel has a total of 22 breaker/fuse holder positions. Refer
to the label located next to each panel on the front of the BDFB for
channel mapping.
Step 1.
Remove the return output bus plastic safety covers (see
Figure 16).
Step 2.
Beginning with the bottom bus and working upwards, install
all hot output cables/lugs to the studs located on the back of
each panel and tighten hardware (see Figure 17)
.
Step 3.
Install all return output cables/lugs to the return output studs
located on the return output bus and tighten hardware (see
Figure 18)
.
Step 4.
Route the output cables upwards in an organized fashion by
tying to the lacing bars located throughout the BDFB rack
assembly.
Step 5.
Reattach the return output bus plastic safety covers.
Figure 16. RTN Output Bus Plastic Cover
Figure 17. HOT Output Connections
Figure 18. RTN Output Connections