4.4 Installation on the wooden bases
−
Once the two (2) supports are installed on the casing, put the collector on the wooden
bases. The supports are pre-drilled with four (4) holes of 8 mm (5/16˝) for fixation.
−
The screws for fastening to the wooden bases are provided by the installer.
−
Level the collector by adjusting the casing on the supports. Make sure the top of the
support is higher than the casing to allow installation of the mounting bars between rows
later on during the assembly.
−
For the first collector of the row, install a collector with a mounting flange. (Check that the
mounting flange is on duct connection side)