Commissioning
Proline Promag 55 FOUNDATION Fieldbus
62
Hauser
6
Commissioning
6.1
Function check
Make sure that all final checks have been completed before you start up your measuring point:
• Checklist for "Post-installation check"
• Checklist for "Post-connection check"
6.2
Switching on the measuring device
Once the connection checks have been successfully completed, it is time to switch on the power
supply. The device is now operational.
The measuring device performs a number of post switch-on self-tests. As this procedure progresses
the following sequence of messages appears on the local display:
Normal measuring mode commences as soon as startup completes.
Various measured value and/or status variables appear on the display (HOME position).
!
Note!
If startup fails, an error message indicating the cause is displayed.
PROMAG 55
START-UP
RUNNING
Startup message
▼
PROMAG 55
DEVICE SOFTWARE
V XX.XX.XX
Current software version
▼
FOUND. FIELDBUS
List of installed input/output modules
▼
SYSTEM OK
→
OPERATION
Beginning of normal measuring mode
▼
0 l/s
→
START-UP COIL
Start-up coil current
Æ