VENTING FIREPLACE - TOP (continued)
Below Grade Installation
When it is not possible to meet the required vent terminal clearances
of 12” (305mm) above grade level, a snorkel kit is recommended.
It allows installation depth down to 7” (178mm) below grade level.
The 7” (178mm) is measured from the center of the horizontal vent
pipe as it penetrates through the wall.
Ensure the sidewall venting clearances are observed. If venting
system is installed below ground, we recommend a window
well with adequate and proper drainage to be installed around
the termination area.
TYPICAL BASEMENT INSTALLATION
Figure 26
Examples of possible venting systems using one 90° elbow. Eight
feet is listed as minimum vertical vent run with 20 feet of maximum
horizontal vent run. Vertical dimensions are based on centerline to
centerline of pipe. Horizontal dimensions are based on centerline
of pipe to end of termination.
Figure 27
Examples of possible venting systems using two 90° elbows.
V is listed as minimum vertical dimensions and H1 + H2 is listed
as total of maximum horizontal dimensions. The maximum vertical
and horizontal distances for two 90° elbows as shown in
Figure
28
is 20 feet.
Attention: Refer to
Figure 23
for additional venting requirements.
Figure 28
Содержание DVP42DP31N-2
Страница 21: ...31457 1 0513 Page 21 Figure 32 Figure 33 Figure 34 EXAMPLES TOP VENT RUN...
Страница 37: ...31457 1 0513 Page 37 Figure 63 MILLIVOLT STANDING PILOT WIRING DIAGRAM...
Страница 58: ...31457 1 0513 Page 58 PARTS VIEW...
Страница 67: ...31457 1 0513 Page 67 APPLIANCE SERVICE HISTORY Date Dealer Name Service Technician Name Service Performed Notes...