InstallatIon, operatIon and maIntenance InstructIons

8.2 reassembly

refer to the exploded parts drawing in 
Section 11 for additional reference during 
disassembly and reassembly of the gagecocks.
1.  Prepare for installation of new packing by 

cleaning all packing chambers and glands 
of upper and lower gagecocks.

2.  on Series K2 gagecocks, replace bonnet (20) 

and bonnet nut (21) and tighten securely in 
place.

3.  Slip stem packing retainer (18) on stem.
4.  install new stem packing (25) and stem 

packing gland (19) on stem.

5.  Thread stem assembly into gagecock by 

turning clockwise until stem seats and then 
back off one turn.

6.  assemble stem packing nut (26) and tighten 

in place.

7.  assemble handwheel (28) or lever (261), 

nameplate (163) (lower gagecock only) and 
handwheel nut (30) on stem and tighten 
securely in place.

8.  replace glass packing nut (37), glass 

packing gland (36) and new glass packing 
(34) on each end of tubular glass (48).

9.  loosen vessel coupling nut (13) of the upper 

gagecock.

10. With upper gagecock turned (approximately 

⅛ turn) counterclockwise from vertical, 
insert one end of tubular glass (48) into 
the stuffing box connection in the upper 
gagecock to sufficient depth to insure 
clearance of the lower gagecock.

11. rotate the upper gagecock clockwise to the 

original position while holding the tubular 
glass (48) in place with upward force to 
insure its clearing the lower tubular glass 
connection. check vertical alignment of 
gagecocks.

12. Slide tubular glass (48) down into lower 

gagecock stuffing box connection to a 
positive stop.

13. Tighten vessel coupling nut (13) on upper 

gagecock.

14. Tighten glass packing nut (37) on both upper 

and lower gagecocks.

15. close both gagecocks by turning handwheel 

(28) or lever (261) clockwise until stem 
seats.

16. replace guard rods (40) if required.

refer to Section 6 for operation of the gagecock 
when returned to service.

9 dIsPOsal at end OF useFul lIFe

Penberthy Series N2 and K2 gagecocks are 
used in a variety of fluid applications. by 
following the appropriate federal and industry 
regulations, the user must determine the extent 
of preparation and treatment the Series N2 and 
K2 gagecocks must incur before their disposal. 
a Material Safety Data Sheet (MSDS) may be 
required before disposal services accept certain 
components.
Metal, glass and polymers should be recycled 
whenever possible. refer to order and 
relevant technical data sheets for materials of 
construction.

10 telePhOne assIstanCe

if you are having difficulty with your Series N2 
or K2 gagecock, contact your local Penberthy 
distributor. You may also contact the factory 
direct at (956) 430-2500 and ask for an 
applications engineer. So that we may assist 
you more effectively, please have as much of 
the following information available as possible 
when you call:

- Model #
- Name of the company from whom you 

purchased the Penberthy Series N2 or K2 
gagecocks

- invoice # and date
- Process conditions (pressure, flow rates, tank 

shape, etc)

- a brief description of the problem
- Trouble shooting procedures that failed

if attempts to solve your problem fail, you may 
request to return your Penberthy Series N2 
or K2 gagecocks to the factory for intensive 
testing. You must obtain a return authorization 
(r.a.) number from emerson before returning 
anything. Failure to do so will result in the unit 
being returned to you without being tested, 
freight collect. To obtain an r.a. number, the 
following information (in addition to that above) 
is needed:

- reason for return
- Person to contact at your company
- 'Ship-to' address

There is a minimum charge for evaluation 
of non-warranty units. You will be contacted 
before any repairs are initiated should the cost 
exceed the minimum charge. if you return a 
unit under warranty, but it is not defective, the 
minimum charge will apply.

nOtes

grafoil

®

 is a registered trademark of graftech, inc.

Содержание Penberthy N2 Series

Страница 1: ...ges It is expressly understood that Emerson is not responsible for damage or injury caused to other products buildings personnel or property by reason of the installation or use of its products This is Emerson s sole warranty and in lieu of all other warranties expressed or implied which are hereby excluded including in particular all warranties of merchantability or fitness for a particular purpo...

Страница 2: ...letely Reverse acting ball checks are available for vacuum service Trim wetted parts that mechanically control the fluid path from the vessel to the tubular glass or other apparatus The ball and stem act to seal and release the fluid In the event of mechanical failure the ball will seat to prevent large quantities of the contained fluid from exiting the vessel Fluid is allowed to exit the vessel i...

Страница 3: ... kPa at 300 F 184 C to 100 F 38 C 610 psig 4210 kPa at 500 F 260 C 450 psig 3100 kPa at 750 F 399 C Pressure temperature ranges in the table above are subject to the limitations of the tubular glass See Table 3 below Table 3 tubular glass ratings 16 mm and 19 mm OD Center to center distance for vessel connections Inches mm No corrosion up to 150 F 66 C Steam boiler service up to 425 F 218 C High p...

Страница 4: ...ot attempt any installation Notify carrier immediately and request damage inspection Refer to exploded view drawing in Section 11 to inventory parts 4 1 User rating inspection The user should confirm that 1 The gagecock set model number and pressure temperature rating stamped on nameplate conforms to the description on the user s purchase order 2 The operating conditions described in the purchase ...

Страница 5: ...s should be evaluated regularly by the user for purposes of maintenance 1 Leakage around stem area 2 Internal stem leak 3 Leakage around stuffing box connection 4 Internal or external corrosion The user must determine an appropriate maintenance schedule necessary for his or her own specific application upon evaluation of his or her own operating experience Realistic maintenance schedules can only ...

Страница 6: ... user s responsibility to choose a material of construction compatible with both the contained fluid and the surrounding atmosphere Broken tubular glass replacement follow steps 7 through 12 of the Disassembly and 10 through 16 of the Reassembly instructions 8 Removal Disassembly Reassembly Warning Use only qualified experienced personnel who are familiar with tubular gagecock equipment and thorou...

Страница 7: ... to Section 6 for operation of the gagecock when returned to service 9 Disposal at end of useful life Penberthy Series N2 and K2 gagecocks are used in a variety of fluid applications By following the appropriate federal and industry regulations the user must determine the extent of preparation and treatment the Series N2 and K2 gagecocks must incur before their disposal A Material Safety Data Shee...

Страница 8: ...igure 2 Neither Emerson Emerson Automation Solutions nor any of their affiliated entities assumes responsibility for the selection use or maintenance of any product Responsibility for proper selection use and maintenance of any product remains solely with the purchaser and end user Penberthy is a mark owned by one of the companies in the Emerson Automation Solutions business unit of Emerson Electr...

Отзывы: