11
Functional Safety Manual
M310/FSM, Rev BA
Installation and Commissioning
April 2017
Installation and Commissioning
Section 4
Installation and Commissioning
Note
For all product information and documentation downloads, see the on-line
Mobrey Magnetic Level Switch web page at
4.1
Installation
The Mobrey Magnetic Level Switch (“level switch”) must be installed as described in the installation
section of the product manual
. Check that environmental conditions do not exceed the ratings in
the specification section.
The Mobrey level switch must be accessible for physical inspection.
4.2
Physical location and placement
The Mobrey level switch shall be accessible with sufficient room for cover removal and electrical
connections, and allow for manual proof-testing to take place.
The switch point is determined by the location of the level switch, and consideration must be given to
allow the safe proof-testing of the level switch by forcing liquid to put the switch into its Fail Safe State.
4.3
Electrical connections
Wiring should be adequately rated and not be susceptible to mechanical damage. Electrical conduit is
commonly used to protect wiring.
Содержание Mobrey Series
Страница 2: ......
Страница 8: ...4 Functional Safety Manual M310 FSM Rev BA Introduction April 2017 Introduction ...
Страница 18: ...14 Functional Safety Manual M310 FSM Rev BA Operation and Maintenance April 2017 Operation and Maintenance ...
Страница 20: ...Proposed Proof test Procedure April 2017 Functional Safety Manual M310 Rev BA Proposed Proof test Procedure 16 ...
Страница 25: ......