7
8.
Remove the PCS cabinet from its packaging and
stand upright. (not shown). Remove the front
cover.
9.
Assemble and mount the leveling bracket as
shown in steps 3 and 4 above.
CAUTION! The PCS cabinet is heavy. Mechanical
lift recommended.
10.
Lift the PCS cabinet onto the wall mounting
bracket.
11.
Slide the PCS cabinet to the left such that it aligns
with the alignment tab on the mounting bracket.
12.
From the rear side of the cabinet, spin the lower
levelling bracket (in/out) until the cabinet is
vertically plumb (level) to the wall (as shown in
step 7).
WARNING! The mounting bolts of the flange
assembly are required to be fully secured, as they
provide the chassis grounding for the battery
cabinet. Torque nuts as specified in the
specification tables provided in this manual.
13.
Insert the PCS cabinet coupling gasket between
the two cabinets (lower-front). Slide the battery
cabinet towards the left until mating to the gasket.
14.
Place the coupling plate inside the PCS cabinet
and insert the four mounting bolts and washers
through to the battery cabinet side.
15.
Place star washers on the bolts on the battery side
of the cabinet.
16.
Mount the battery cabinet side coupling plate, and
fasten with the lock nuts. Torque to 10 – 15 in-lbs.
17.
Continuity test: Check the continuity between the
cabinets using an Ohm meter. The test reading
must be zero Ohms at a bare metal point inside
each of the PCS and battery cabinets.
18.
Optional: (This is not a load bearing anchor –
anchored conduit runs to the PCS are
satisfactory). Install screws in leveling plates for
PCS and battery cabinets by inserting a
screwdriver through the hole on the backside of
the cabinets.
19.
Plug hole on back of cabinet using by inserting the
hole plug from the front side.
10
11
13
14
15
16
18
19
Optional (hardware not
included)
Figure 3: PCS cabinet and inter-cabinet coupler installation.
Содержание ACB05U-LP
Страница 29: ...26 THIS PAGE INTENTIONALLY LEFT BLANK...