19
E D G E I Q H A N D B O O K
6.
A T T A C H S A F E T Y L A B E L S
The following safety labels must be attached for all installations
with solar
, prior to commissioning the unit, to
inform other electricians who attend the site after the installation of the EdgeIQ.
6.1. Place Label 1 and Label 2 on the front cover of the EdgeIQ unit
Label 1: Dual supply isolation
Label 2: Shutdown Procedure (including Dual supply isolation steps)
EdgeIQ SHUTDOWN
PROCEDURE
Isolatingthe solar supply:
1. Turn off the solar‘Supply Main
Switch’.
2. Turn off the ‘DC PV Array Isolator’.
Isolating the network AC supply:
1. Turn off the installation’s Main Switch
Circuit Breaker.
Note:
Start-up procedure is the reverse of
the shut-down procedure
Important:
For connection or
disconnection of the EdgeIQ, ensure
complete isolation
of
both
the incoming
supply and any solar or other embedded
generator supplies.