11
Installation
ECOWATER
S Y S T E
M S
9. PRESSURE TESTING FOR LEAKS
TO PREVENT EXCESSIVE AIR PRESSURE IN
THE FILTER AND PLUMBING SYSTEM, DO THE
FOLLOWING STEPS IN ORDER
a.
Open two or more filtered water faucets, both hot
and cold.
b.
Referring to Figure 8, turn the bypass valves to
service position.
c.
Slowly open the main water supply valve.
d.
Close the filtered water faucets after both of the
following occur.
-- water runs smoothly, with no air bubbles
-- you can smell the sanitizing (page 6) bleach odor
at the faucets
e.
Check your complete installation for leaks. If re-
work is required, be sure to observe precautions in
step 6.
10. CONNECT ALL LEADWIRES
a.
Connect the wire harness to the valve switch and
to the timer, Figure 9. The switch is on the valve, by
the large gear. Snap the sensor onto the outport of
the valve.
NOTE:
Check to be sure the connector is secure on
the back of the timer.
b.
Attach the connector, on the valve motor leadwire,
to the the matching connector on the faceplate timer.
c.
Connect the power cable leads to the back of the
timer.
d.
Connect the leads from the relay box to the back
of the timer. Secure the wire using the strain relief
and attaching it to the valve.
11. CONNECT AIR PUMP
a.
On the floor or a shelf nearby the filter, fasten the
air pump in place.
b.
Install the air filter (if required) and tubing connec-
tor fitting.
c.
Connect the tubing from the check valve, on the
adaptor, to the connector fitting on the air pump.
d.
Plug the pump into the relay box connector.
12. CONNECT TO ELECTRICAL POWER
Plug both the transformer and relay box into continu-
ously “live”, grounded, 115V--60Hz house electrical
outlets, approved by local codes.
13.
TO COMPLETE INSTALLATION, DO THE PRO-
GRAMMING STEPS ON PAGES 12 AND 13.
NOTE: WATER HEATER START--UP ON PAGE 13.
M
24V
BACK OF TIMER
POSITION
SWITCH
24VAC
TRANSFORMER
FIGURE 9
GND
OUT
+5
TURBINE
SENSOR
NC
NO
RELAY BOX
TO 115V
OUTLET
CONNECT TO
AIR PUMP