EcoFoot5D Install Guide V1.1-FINAL
Page 17 of 19
January 25, 2018, ES10560
ecolibriumsolar.com
Step 4 – Install Hardware on Bases
4.1
Install Elevator Bolts and Nut Coupling into EcoFoot 5D bases. Torque to 8 ft-lb.
Repeat process on both Bases.
Step 5 – Install Ballast Tray and secure to Mid-Span Support & Bases
5.1
Referring to Step 5 of the Installation Guide, install Ballast Tray. Line up slots with attachment stud,
base hardware and Mid-Support.
5.2
Torque fastener into Mid-Span Support to 14 ft-lbs. through slot on Ballast-Tray.
5.3
Fasten Ballast Tray to base with Washers and Serrated Hex Bolts on both bases.
Torque to 8 ft-lb.
5.4
Install Washer and Serrated-Flange Nut onto Preferred Roof Attachment in order shown below.
Torque Serrated -Flange Nut to 14 ft-lbs.
5.5
Roof Attachment installation complete for Seismic Rated Attachment System.
Nut Coupling
and Elevator Bolts
Washers and
Serrated Hex
Bolts
Washer and
Serrated Hex Nut
Serrated
Hex Bolt