EcoFoot5D Install Guide V1.1-FINAL
Page 8 of 19
January 25, 2018, ES10560
ecolibriumsolar.com
Install EcoFoot5D in 6 Simple Steps
Step 1 – Install Preassembled Universal Clamps into Bases
1.1
Place Lower and Upper Universal Clamp into EcoFoot5D Base as shown.
Note: The Upper Clamp includes a post and nut to install the Wind
Deflector as shown in Step 6.
1.2
Push Clevis Pins completely into EcoFoot5D Base to secure Rocker.
Step 2 – Position Array
2.1
Snap two chalk lines on roof denoting outside edges of the
EcoFoot5D Bases, per project drawing. Start from the
north or south edge. Ensure chalk lines are square.
2.2
Place EcoFoot5D Bases in approximate position throughout
the array
.
Installation Tips
Only install Clamps
where modules will
rest.
See Step 3 for
correct placement
and orientation of
Clamps.
Base
Lower Clamp
Upper Clamp
Clevis Pin
Clevis Pin
Bases
Chalk Lines
Installation Tips
As you build the
array, panels will
space the Bases.
Roughly place a few
rows of Bases at a
time so that they are
within reach of final
location.