Introduction

1.

The boiler and all associated equipment must be installed and used in accordance with the installation design, all applicable
legal regulations and technical standards and with the manufacturer’s instructions. The boiler may be used only for the purpose
for which it is intended.

2.

The boiler may be installed only in an environment which it is designed for.If the boiler is delivered to the client by the same
person who installs it, he must give the user also all accompanying boiler documentation (in particular User Guide, Service Book,
etc.). Until the boiler is put into service, the original packaging must be kept in case the boiler has to be transported again.

3.

After installation, the boiler must be put into operation by a service organisation authorised by the manufacturer.

4.

The boiler complies with regulations applicable in the European Union. When used in the conditions of countries outside at
EU, any deviations from local regulations must be identified and rectified.

5.

In the event of a defect, call an authorised manufacturer’s service organisation–any unauthorised interference may damage
the boiler (and possibly also associated equipment!).

6.

The service technician putting the boiler into operation for the first time must show the user the various parts of the boiler and
how to control the boiler, with the boiler safety elements, their signals and appropriate user reaction to them, with fundamental
parts of the boiler and their controls. If the boiler is delivered to the client by the same person who installs it,he must make
sure that the original packaging is available in case the boiler has to be transported again.

7.

Check the delivery for completeness.

8.

Check whether the model and type supplied is suitable for the required use.

9.

Whenever you are not certain how to control the boiler, study appropriate instructions in this Operation and Installation Guide
carefully and proceed accordingly.

10. Never remove or damage any markings and signs on the boiler. Keep the original packaging until the boiler has been put

into service, in case the boiler has to be transported again.

11. When making any repairs, only original parts must always be used. It is forbidden to make any changes to the boiler’s internal

installation, or to interfere with it in any way.

12. At the end of its life cycle, the boiler its package and its parts must be disposed of in a way avoiding harm to the environment.

13. The manufacturer disclaims any responsibility for damages caused by the failure to abide by:

          ■

   The conditions stipulated in this Operation and Installation Guide;

          ■

   Applicable regulations and standards;

          ■

   Sound installation and operation procedures; and

          ■

   Conditions stated in the Warranty Certificate and the Service Book.

Situations might occur in practice, when the following essential precautions must be taken:

          ■

   Shut the boiler down every time when there are any (even temporary) flammable or explosive fumes present on the premises

from which combustion air is supplied to the boiler (e.g. from paint when painting, laying and spraying molten substances,
from gas leakage, etc.);

          ■

   If it is necessary to drain water from the boiler or from the whole system, the water must not be dangerously hot; and

          ■

   If there is any leakage from the boiler’s heat exchanger, or when the exchanger is clogged up with ice, do not attempt to

start up the boiler until normal operating conditions have been restored.

Ensuring safety of equipment and people

     The boiler (and all accessories) complies with the requirements of EN 303-5 its updates and all relevant European standards.

     In order to run and operate the boiler in accordance with the purpose for which it is designed in actual conditions of use

(hereafter referred to only as use), it is necessary to abide also by additional requirements the most essential ones of which
(i.e. those which must not be omitted) are found in the related regulatory documents.

     In addition to the above mentioned documents, it is necessary when using the boiler to proceed in accordance with this

Operation and Installation guide and the accompanying boiler manufacturer’s documentation.

     Any interference by children, persons under the influence of narcotic drugs, certified persons, etc., when using the boiler, must

be prevented.

Содержание Evo Multi Fuel Boiler

Страница 1: ...Angus Evo Multi Fuel Boiler Installation Operation and Maintenance Manual...

Страница 2: ...rols 13 Starting a fire 13 Setting outlet water temperature 13 Stoking 14 Overnight heating mode 14 Removing solid combustion residuals 14 Dewing and tarring 14 Boiler shutdown 14 Short term shutdown...

Страница 3: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL 1 Information on the boiler plate The boiler Serial No is shown on the plate which is attached to the cover panel of the cast iron body fig 01...

Страница 4: ...MANUAL 2 Boiler dimensions fig 02 Boiler packaging dimensions fig 03 EV 03 EV 04 EV 05 EV 06 L mm 609 709 809 909 EV 03 EV 04 EV 05 EV 06 L mm 665 765 865 965 Notice Please obey to the meanings of th...

Страница 5: ...e Control C 30 90 Maximum Pressure of System bar 4 Minimum Pressure of System bar 0 4 Boiler Water Content L 16 33 20 30 24 27 28 24 m3 0 01633 0 0203 0 02427 0 02824 Exit Flue Connection Diameter mm...

Страница 6: ...be increased approximately 10 FOR COAL MODEL HEAT OUTPUT kW HEAT OUTPUT kCAL MAX HEATING AREA UNC M2 Solid Fuel 03 17 14 617 146 Solid Fuel 04 27 23 216 232 Solid Fuel 05 34 29 235 292 Solid Fuel 06...

Страница 7: ...ep the original packaging until the boiler has been put into service in case the boiler has to be transported again 11 When making any repairs only original parts must always be used It is forbidden t...

Страница 8: ...iler body is equipped with necessary pipe sections for water connection It also has brackets for fitting thermostat sensors and brackets on feet for fastening the boiler to the base Attached to the ca...

Страница 9: ...ing the safety and the control elements remember to meet the principles of work safety If replacing of safety device and of thermo mechanical output regulator is necessary please use recommended devic...

Страница 10: ...Temperature safety valve The Angus Evo boilers can be equipped with a safety heat exchanger with thermal safety valve as an optional which ensures dissipation of excessive heat without additional devi...

Страница 11: ...p 3 Cold Water Feed 8 Heating System 4 System Safety Valve 3 bar 1 2 9 Open Expansion Tank 5 NRV Open type expansion tank must be equipped with the highest level in the entire hydraulic system The exp...

Страница 12: ...sion Tank 5 Four Way Mixing Valve 3 Radiator fig 11 1 Boiler 2 Laddomat 21 60 operated by Flue Thermostat 50 300 C 3 NAD or NADO Accumulator Tank 4 Immersion Heater 5 Three Way Mixing Valve 6 Circulat...

Страница 13: ...en for an appropriately sized expansion vessel on the central heating circuit before the return to the boiler and a safety group on the primary flow It is essential to ensure that the expansion vessel...

Страница 14: ...AL 12 fig 15 fig 16 1 Boiler 2 Safety Group automatic air vent pressure reducing valve and pressure gauge 3 DHW Cylinder 4 CH Pump 5 Heating System 6 Four Way Mixing Valve 7 NRV 8 Expansion Vessel 9 A...

Страница 15: ...with the boiler cold or cooled down otherwise the boiler segments may crack Operation and controls Starting a fire Check on the thermo manometer whether there is enough water in the heating system Ope...

Страница 16: ...the boilers inside walls When running the boiler with low water temperature usually below 65 C or when using damp fuel water condensates in combustion gases and the condensate runs down the boiler s...

Страница 17: ...esult in inadequate chimney thrust The boiler must be cleaned regularly at least once a month which is done with a steel brush through an open boiler door After taking front section plate off all boil...

Страница 18: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL 16 fig 19 fig 20 fig 21 fig 22...

Страница 19: ...ways be used Warranty and warranty conditions Angus Evo boilers are covered by warranty specified in the Warranty Certificate Service Book and User and Installation Guide chapter Introduction Installi...

Страница 20: ...essure We recommend installing a sludge trap upstream of the boiler i e on hot water return pipe The sludge trap design should allow emptying in regular intervals without the need to drain a lot of ho...

Страница 21: ...g the entire depth of the boiler body If the boiler is installed in a cellar we recommend to put it on a socket at least 50mm high positioning the boiler in the middle To comply with standards at leas...

Страница 22: ...utlet when the boiler is operating Installation procedure Place the boiler body on a non flammable materials Install a thermal safety valve After connecting the boiler to the heating system screw fill...

Страница 23: ...INSTALLATION OPERATION AND MAINTENANCE MANUAL 21 Angus Evo boiler parts fig 25 fig 26...

Страница 24: ...EV PM 140 EV PM 140 EV PM 140 25 Thermostat Bulb Segment EV 20080124 EV ST 141 EV ST 141 EV ST 141 EV ST 141 26 Stopper 3 4 EV 20080125 EV PM 131 EV PM 131 EV PM 131 EV PM 131 27 Thermostatic Regulato...

Страница 25: ...essary when the required volume is less than 300L Transportation and storage The manufacturer handles the boiler that is on a palette and secured against shifting with screws The boiler may not be tra...

Страница 26: ...arnings A sufficient flue draft of the flue gas system is the basic requirement for the correct functioning of the boiler It fundamentally affects its performance and efficiency Therefore heed the fol...

Страница 27: ...ted Boiler is heating but radiators are not Quality of the fuel might be low and or the moisture content of the fuel maybe high Operational instructions are not fulfilled Tar existing on surface of he...

Страница 28: ...For more information please visit our website www ecoangus co uk 01934 862642 07739 174511 07970 901273 ecoangus aol com 2068 Designed and produced by...