Eclipse RatioAir v1 - Installation Guide No. 115, 4/7/06
1
C
heCk
l
ist
a
fter
i
NstallatioN
To verify the system was properly installed, perform the
following checks:
1.
Be sure there are no leaks in the gas lines.
2.
Be sure all the components contained in the flame
monitoring and control system are properly installed. This
includes verifying that:
•
all the switches are installed in the correct locations.
•
all wiring, pressure, and impulse lines are properly
connected.
3.
Be sure all components of the spark ignition system are
installed and functioning properly.
4.
Be sure the blower rotates in the proper direction. If the
rotation is incorrect, have a qualified electrician rewire the
blower to rotate in the proper direction.
5.
Be sure all valves are installed in the proper location and
correctly oriented relative to the flow direction.