6.3 START UP
• Before start up, satisfy of conditions of 6.2.1 and 6.2.2
• Make sure that all equipments, except transformer, are adjusted max value of voltage or
current and choosen properly.
• All electrical connection must be checked by authorized personnel.
• Safety zone must be allocated while energizing transformer and all living creatures must be
taken out of zone.
• First energizing of the transformer must be operated off-load. After inspecting the usual
conditions of noise level, temperature and oil level; the transformer would be loaded.
7. OPERATING AND MAINTENANCE
Transformers do not require any particular maintenance. However, to guarantee good operation,
a few periodic checks should be carried out as follows.
• Oil level and oil leakage should be observed periodically. In case any decrease in oil level,
- If transformer is conservator type; refined oil with the same specifications should be added.
Oil leakage must be prevented with proper procedure.
- If transformer is hermetically sealed, the manufacturer should be informed as soon as possible.
• Dehydrating breather should be checked; in case of malfunctioning, it must be replaced. (for
conservator type transformers)
• Buchholz Relay should be checked periodically. If there is gas accumulation, it must be
released after the reason is detected. Functions of relay should be controlled annually.
• Oil temperature should be checked through thermometer; if there is overheating, reasons
should be detected.
• Grounding resistance should be checked annually. (It must not exceed 5 Ω.)
• Maintenance and inspections should be carried on while transformer is de-energized.
• Bushings always should be cleaned and their physical status should be properly checked.
• In case of breaks and cracks in bushings, please contact with the manufacturer for
replacement. Bushing should be stocked in vertical position and dry conditions.