13. Install the front cover (previously removed) by carefully lowering the cover onto the bottom mounting
bolts. Secure the top of the cover with the two retained mounting bolts and tighten the bottom bolts.
14. Once the battery cabinets are installed and wired, return to the applicable Eaton 93PM UPS Installation and
Operation manual, listed in paragraph
, to complete the UPS wiring.
Figure 17. Interface Terminal Locations – Eaton 93PM IBC–SW
Interface
Terminal TB2
Table 7. IBC TB2 Interface Connections
Terminal
TB2
Name
Description
10
Thermal Sensor
Contact used to signal a battery temperature out of specification and
to turn off the battery charger to prevent thermal runaway.