Enterprise Power Solutions Installation and Operation Guide
18
Copyright © 2008 Eaton Corporation. All Rights Reserved.
IPN 997-00012-56C September 2008
"
Circuit breaker cover
#
Load circuit breaker (1 of 10 shown)
$
Circuit breaker blank covers (to cover
unused circuit breaker positions as
required)
Procedure complete
Task 3 - Mount the EPS2/EPS5 in the Rack
Step 1 - Check clearances
The EPS2/EPS5 requires the following clear space:
Front:
adequate space for access and ventilation for rectifiers-
600mm (24") minimum recommended.
Rear:
adequate space for ventilation and access to input and
output terminals, and battery connectors
Below:
adequate space for ventilation and to route wires
connected to the output terminals (recommended 1U
minimum).
No heat source greater than 50°C below the EPS2/EPS5.
Sides:
if required, adequate space for access to protective ground
terminal and telecom ground terminal.