Installation
Eaton 93E Integrated Transformer Cabinet (ITC) Installation Manual P-164000074—Rev 3
www.eaton.com/powerquality
4-27
4.5
Initial Startup
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified on page W-1 become void. This service is offered as part of the sales contract for the
UPS. Contact an Eaton service representative in advance (usually a two-week notice is required) to reserve a
preferred startup date.
4.6
Completing the Installation Checklist
The final step in installing the ITC is completing the following Installation Checklist. This checklist ensures that
you have completely installed all hardware, cables, and other equipment. Complete all items listed on the
checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain
the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
installation tasks other than verifying software and operating setup parameters. Service personnel may request
a copy of the completed Installation Checklist to verify all applicable equipment installations have been
completed.
Installation Checklist
o
All packing materials and restraints have been removed from each cabinet.
o
The ITC is installed on a level floor suitable for computer or electronic equipment.
o
The ITC is placed in its installed location
o
All conduits and cables are properly routed between the ITC, UPS, and IAC-B.
o
All power cables are properly sized and terminated.
o
A ground conductor is properly installed.
o
All terminal cover plates are installed.
o
Air conditioning equipment is installed and operating correctly.
o
The area around the UPS system is clean and dust-free.
o
Adequate workspace exists around the ITC and other cabinets.
o
Adequate lighting is provided around all ITC and UPS equipment.
o
A 120 Vac service outlet is located within 7.5 meters (25 feet) of the ITC and UPS equipment.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for
the first time.
Содержание 93E 30ITC
Страница 1: ...Eaton 93E Integrated Transformer Cabinet 30ITC and 60ITC Installation Manual ...
Страница 2: ......
Страница 3: ...Eaton 93E Integrated Transformer Cabinet 30ITC and 60ITC Installation Manual ...
Страница 73: ......
Страница 74: ... P 164000074 3 P 164000074 3 ...