UPS 40 – 160 kVA, 400V 50/60 Hz output
User’s and Installation Guide
1023294
Revision C
39
The System Setup Level 1 screen can be used to set the UPS date and time, the serial ports,
change the Level 1 password, and logout of Level 1. In addition, the Level 0 functions are
available. Use the UP or DOWN pushbuttons to highlight the setup function screen desired,
then press the SELECT pushbutton to display the function screen.
For example, select COM PORT SETUP from the System Setup Level 1 menu to display the
Serial Port Setup screen. This screen allows selection of the serial COM port to set up. Use the
UP or DOWN pushbuttons to highlight the COM port to be set up, then press the SELECT
pushbutton. To return to the System Setup screen, press the RETURN pushbutton.
The COM Setup screen is used to change and save the settings for the serial communication
ports. The COM port number selected from the Serial Port Setup screen will be displayed. If the
changes are not wanted, the ABORT pushbutton may be used to return to the Serial Port Setup
screen.
Use the UP or DOWN pushbuttons to highlight the setting to be changed. Use the SELECT
pushbutton to toggle through the values for the setting to make the change. Press SAVE or
ABORT. Once the action is completed, the Serial Port Setup screen appears.
Figure 31
. Serial Port Setup Screen at System Setup Level 1.
The Level 1 screen will timeout after 60 minutes, or can be logged out at any time by selecting
the LOG OUT function from the menu screen.
6.2.5 Load Off Screen
The Load Off screen appears when the LOAD OFF pushbutton is selected from the Main Menu
bar or System Controls Menu bar. This screen allows the LOAD OFF process to be aborted if the
LOAD OFF pushbutton was pressed accidentally.
Figure 32
. Load off screen.