6. Initiate the system evacuation.
Evacuate the system down to 230 MICRONS
as
read on the digital micron gage. After 230 microns has been achieved, turn off the
LP and HP valves and turn “OFF” the vacuum pump
. Reading the digital micron
gage, the system pressure must not exceed 280 MICRONS WITHIN 5
MINUTES.
If pressure rises to greater than 280 microns, open LP and HP valves,
crack the refrigerant valve and allow just enough refrigerant into the system until
20 inches of Hg vacuum is read on the LP gage. Close the refrigerant valve, and
initiate the evacuation process again and until the above conditions are met.
Figure 15. Typical Evacuation & Initial Charge Set-up for SC, SD and SCW
Compressor Models (SC model shown).
Содержание SCW Series
Страница 8: ...SCW 410 QS 05 12 Page 8...
Страница 9: ...SCW 410 QS 05 12 Page 9 Figure 5 SCW Connections for R 410A...
Страница 10: ...SCW 410 QS 05 12 Page 10 Figure 6 SCW Internal Flow Schematic...
Страница 11: ...SCW 410 QS 05 12 Page 11 Figure 7 SCW Piping...
Страница 15: ...SCW 410 QS 05 12 Page 15 Figure 10 SCW Electrical Ladder Diagram 230 1 60...
Страница 16: ...SCW 410 QS 05 12 Page 16 Figure 11 SCW Electrical Schematic 230 1 60...
Страница 17: ...SCW 410 QS 05 12 Page 17 Figure 12 SCW Series 230 3 60 Electrical Ladder Diagram...
Страница 18: ...SCW 410 QS 05 12 Page 18 Figure 13 SCW Series 230 3 60 Electrical Schematic...
Страница 19: ...SCW 410 QS 05 12 Page 19 Figure 14 Part 1 of 2 SCW Field Wiring Diagram Reference Figure 8...
Страница 20: ...SCW 410 QS 05 12 Page 20 Figure 14 Part 2 of 2 SCW Field Wiring Diagram Reference Figure 9...
Страница 28: ...SCW 410 QS 05 12 Page 28 Figure 21 Charging and Superheat Adjustment Process...