MK1 CLEAR ROOF PANEL (Optional) 

Step 1: 

Position Roof Sheets at each end. Leave a gap where the Clear Panel is to be fitted. Nail on first Roof Sheet 

(refer to step 2 MK1 Roof). 

Step 2:

 Where the Clear Roof Panel is to be positioned, nail a 45x45mm Bevelled Edge Support on each side of the 

Ridge Beam. 

(fig. 1)

 

Step 3:

 Position Clear Roof Panel and Flat Roof Sheet (or second Clear Panel). The Flat Roof Sheet underlaps one sheet 

and overlaps the other. The Clear Roof Panel OVERLAPS both Roof Sheets. Ensure sheet joins are flush at the 

outside edge then rivet flat sheets to pressed sheets. Two rivets per join. Centralise Roof at the other end and nail 

in place. 

Step 4:

 Ensure Ridge Beam is straight, then nail the Clear Panel and Flat Roof Sheet (or second Clear Panel) to 

45x45mm Bevelled Edge Supports using one 30mm Clout per Pan. Run two generous beads of Silicone on the 

under side of the Pressed Capping Sheet. Position Pressed Capping Sheet on Ridge Beam and nail in place us-

ing three 40mm Weatherseals. Nail one 40mm Weatherseal into Ridge Beam beside each overlap (one nail per 

sheet). 

Step 5:

 At the Back set up a String line in the centre of the Top Plate. Ensure Top Plate is straight and nail off, one 40mm 

Weatherseal per Pan. Repeat at the front. 

Note: 

When nailing through the Clear Panel, pre-drill a 6mm hole. 

11 

TOP PLATE 

JACK STUD 

RIDGE BEAM 

45 x 45 BEVEL 

75mm NAIL 

SILICONE 

30mm CLOUT 

PRESSED 

WEATHERSEAL NAIL 

PRESSED 

CLEAR ROOF 

FLAT ROOF 

Содержание Kiwi MK1

Страница 1: ...Quality Built In ASSEMBLY INSTRUCTIONS MK1 BASE SIZE 1715mm x 1715mm...

Страница 2: ...g your own floor refer to Raised Base Plate section now Do not attempt to build your shed in high winds Beware of sharp edges Protect your eyes and ears Use electric tools with care Use a Safety Trip...

Страница 3: ...ndow Frame Glass Window Hardware Pack 2 000m Roof Sheets Security Double Door Hardware Pack Alarm MA20 Shed light Bolt Down Kit Peg Down Kit 0 975m Flat Roof Sheet 100 12 50mm 75mm Flooring Nails Floo...

Страница 4: ...MK1 TIMBER FRAME 4 1 810 YELLOW YELLOW YELLOW YELLOW YELLOW 45 45 1625 1715 45 45 45 BACK WALL 883 45 45 795 1715 45 45 45 FRONT WALL 883 45 785...

Страница 5: ...each end Pre drilling holes before nailing will prevent timber from split ting Step 5 Carefully roll frame over onto its base Pieces of timber from the packaging may be used to tem porarily brace the...

Страница 6: ...ON To Tack To Tack on a wall sheet means to use minimum nails hammered partly in to hold Wall Sheets in position Should a Wall Sheet need to be re positioned the nails can easily be prized out If a wi...

Страница 7: ...place Step 4 Nailing Off Nail one 30mm Clout each side of the Rib two per Pan into the Top Plates and Bottom Plates Nail Wall Sheets to mid wall Nogs one per pan Nail each corner Wall Sheet to Studs u...

Страница 8: ...ll holes in each corner and nail Window Frame to framing using 50mm nails Step 4 If the Window is in the gable end tempo rarily position the Over Panel above Win dow Frame Following the same angle as...

Страница 9: ...570mm Step 6 From the outside of the shed place glass in Window Frame Attach a Glazing Bead G100 with three rivets to each side of the Window Frame to hold glass in place Pre drilling Glazing Beads is...

Страница 10: ...on the left hand side For sheds with a Clear Roof Panel go to the next page Posi tion the next Roof Sheet Ensure it overlaps correctly then rivet together 400mm down from the centre on both sides Step...

Страница 11: ...he other end and nail in place Step 4 Ensure Ridge Beam is straight then nail the Clear Panel and Flat Roof Sheet or second Clear Panel to 45x45mm Bevelled Edge Supports using one 30mm Clout per Pan R...

Страница 12: ...oor Stop MK1 DOOR Step 3 Remove Door Pre drill holes into each Rib and at similar spacings into Over Door Flash ing At approximately 1 3 in from each end of Door Track put a 50mm nail Fix rivets to re...

Страница 13: ...straight then rivet to Roof one rivet every second Rib Note MK2 shown Note MK2 shown MK1 FLOOR Optional Step 1 Place shed in final position Check the di agonal measurements are the same and the shed i...

Страница 14: ...into Joists Measure and cut Floor Flashing 110 to fit in between Door Jamb Flashings and nail in place using 50mm Clouts MK1 HASP STAPLE Using six rivets and one 50mm clout attach hasp to Door Jamb Fl...

Страница 15: ...on a purpose built floor concrete cobbles ply etc the Wall Sheets will pro trude 20mm below the Base Plate This will stop water flowing in between the Base Plate and Floor The Floor should be made 15...

Страница 16: ...rried out in accordance with instructions below Should the cladding fail to perform as specified above the liability of Riverlea Group Ltd shall in all cases be limited to replacing or repairing the d...

Отзывы: