COMMISSIONING 

 

1.  Check the fastness of all fixings. Ensure that the  

  insulation is fitted correctly and that the radiating  

  surface is not damaged. 

2.  Purge the air from the system using air vents in  

  the mains. 

3.  Check pipe connections for leaks. 

  Refer to Table 2 for test and working pressures. 

4.  Balance the water flow rate through the panel to  

  accepted practice to achieve the specified flow rate. 

5.  Leave this document and any layout drawings with the  

  end-user 

 

 

 

 

 

 

 

Maximum cold test pressure 

12 bar gauge 

Maximum working pressure at 120°C 

6 bar gauge 

Table 2 : 

Recommended test and working pressures 

 

 

 

 

 

 

 

 

 

 

Diagram 8:  Standard joint detail for Evo-Lite Style CG 

 

 

Page 6 of 8 

Содержание Evo-Lite Style CG

Страница 1: ...h may also be shown on the BL drawing DESCRIPTION Evo Lite Style CG comprises aluminium alloy sheet panel bonded to an extruded aluminium channel profile copper tube carrying the hot water is mechanic...

Страница 2: ...suspected at the time of delivery Preparation Evo Lite Style CG radiant panels are intended for horizontal installation within a standard 600mm ceiling grid hence it is important to liase with other t...

Страница 3: ...Diagram 3 Typical section detail for installation Style CG 4T shown 2T similar Diagram 4 Suspension point locations for Evo Lite Style CG Page 3 of 8...

Страница 4: ...sing panel joint clips and M5 nuts provided Refer to Diagram 6 5 Expansion panels should be fitted every 6m of straight panel run and are supplied with expansion hoses fitted in place of the straight...

Страница 5: ...Diagram 6 Installation detail of Evo Lite Style CG standard joint Diagram 7 Installation detail of Evo Lite Style CG expansion joint Page 5 of 8...

Страница 6: ...s for leaks Refer to Table 2 for test and working pressures 4 Balance the water flow rate through the panel to accepted practice to achieve the specified flow rate 5 Leave this document and any layout...

Страница 7: ...el runs Refer to Diagram 2 for typical arrangements in a panel run Dunham Bush will prepare complete baseboard layout drawings for approval which can be used to co ordinate materials and installation...

Страница 8: ...WRITE THE DETAILS OF RADIANT PANELS HERE These details will be required when ordering spares for your Dunham Bush radiant panels STYLE AND No OF TUBES BL DRAWING OR ORDER No DATE OF INSTALLATION Spare...

Отзывы: