Installation and Operation of:
FlexBake 5™ Integrated Ventilation System
Step 3
Remove the Vent Box Cover by removing the 9 (#8-
32) screws from the vent box cover on back of unit.
SAVE SCREWS.
Step 4
Remove the 4 (#8-32) screws from the venturi ring.
SAVE VENTURI RING and SCREWS to reinstall with
the IVS Vent Box.
Step 5
Remove the 4 (1/4-20) nuts from the Cool-down
blower housing tabs securing the Vent Box.
Remove the Facade Vent Box.
SAVE NUTS.
Step 6
Remove the Facade Back Panel by removing the 7
(Tek) screws and the 4 (#8-32) screws.
SAVE SCREWS.
Step 7
Remove the 6 (Tek) screws along each side panel
and remove the Facade.
SAVE SCREWS
NOTE: Save all facade parts removed
for potential reuse, if desired.
Step 8
Remove the 2 screws (#10-24) securing the
Exhaust Duct Extension.
Step 9
Remove the Exhaust Duct Extension and save for
potential reuse with the facade, if desired.
NOTE
: Do not exert excessive force
on the cavity exhaust duct. This must
remain firmly secured and sealed to the