Maintenance of Major Components
- 141 -
4) Measuring pilot bore of flywheel
Install the gauge as below so as for the
gauge stem to contact to the pilot bore of
the surface to be installed. The
eccentrics of the pilot bore of flywheel
should not exceed 0.127 mm at
maximum.
5.5.2. Installing
The center alignment of engine and Generator set is the most important factor for the extension of
performance and life. Although aligning the center perfectly and accurately requires only few minutes, it
is able to prevent unnecessary mechanical trouble at the future.
1) Bed rail
At the installation of Generator set’s bed
rail, use steel, If the bed rail is strong
enough, the center alignment of engine
with Generator gets worse so that the
excessive vibration may occur.
2) Supporting
As in the engine installation, the supporting brackets are used even at the installation of Generator.
The bracket must be solidly fixed at the Generator installing platform and the bed rail.
Dial gauge
Dial gauge
Flywheel
EFM6020I
Engine
Bed rail
Dial gauge
Shim
Supporting bracket
EFM8001I
Содержание P158LE -III
Страница 160: ...Appendix 157 1 P158LE Generator engine assembly EH5OM013 ...
Страница 161: ...Appendix 158 2 P180LE Generator engine assembly EH5OM014 ...
Страница 162: ...Appendix 159 3 P222LE Generator engine assembly EH5OM015 ...
Страница 163: ...Appendix 160 4 PU158TI Power unit engine assembly EH5OM016 ...
Страница 164: ...Appendix 161 5 PU180TI Power unit engine assembly EH5OM017 ...
Страница 165: ...Appendix 162 6 PU222TI Power unit engine assembly EH5OM018 ...