Donaldson Company, Inc.
14
Machine Center Mount with Vertical inlet Hopper
and Vibration Isolators Installation
Vertical inlet hopper and vibration isolators are for
installing a collector on a machine center that is
sensitive to vibration.
1. Carefully lift unit into position over the
machine center and lower into position.
2. Trace bolt hole pattern for vibration isolators
on the base of legs to the machine.
3. Drill four 1/2-in holes into the machine center
for installing the vibration isolators.
4. Fasten the isolators to machine center.
5. Carefully position unit over the isolators and
lower into position.
6. Install and tighten fasteners. Vibration isolator
needs to be torqued to 12.0 ft-lbs.
7. Connect the flexible duct using the hose clamps
to the collector and the machine center collar.
See Inlet Hopper with Flex-Duct Installation
section.
Note:
If machine center has no inlet collar,
order part from Donaldson Parts Express
Line (1-800-365-1331).
8. Install P-trap or 1 1/2-in NPT plug. If a plug is
used, a shallow pool of coolant will be present
at the bottom of the hopper before it drains
down the inlet duct.
sealant
vertical inlet hopper
hose clamp
flex-duct
hose clamp
leg
vibration
isolator
WSO unit
P-trap drain
inlet collar
Internal Hopper
View
Inlet Hopper with Vibration Isolators Installation, WSO 15 shown
Содержание WSO 10
Страница 1: ...IOM AK0300601 Revision 2...
Страница 9: ...WSO 10 15 and 20 9 This Page Intentionally Left Blank...
Страница 15: ...WSO 10 15 and 20 15 This Page Intentionally Left Blank...
Страница 24: ......
Страница 27: ...WSO 10 15 and 20 27 This Page Intentionally Left Blank...
Страница 35: ...WSO 10 15 and 20 35 e t a D d e m r o f r e P e c i v r e S s e t o N Service Notes...
Страница 36: ...Donaldson Company Inc 36 Service Notes continued e t a D d e m r o f r e P e c i v r e S s e t o N...
Страница 37: ...This Page Intentionally Left Blank...
Страница 38: ...This Page Intentionally Left Blank...
Страница 39: ......