6050-065-D-2-16
11
Arm
Rotation Area
Closed Gate
5”
1.5 Post Mount
1.6 Arm and Gate Bracket Installation
10”
18.5”
34”
6”
Do not
insert the locking pin or padlock
into the crank arm. It will be installed
after arms have been adjusted.
Do not
secure the elbow assembly
to the arms until the arms have
been adjusted. (See next page).
Mount the post base into the concrete
before installing the operator.
The post mount installation will allow
the operator to be mounted low enough
to attach the gate bracket to the lower
gate rail if desired.
Adjust the locknut on the crank power
arm so that it is snug against the
washer, but will still allow the crank arm
to rotate with little force.
This is the
operator’s manual release option when
the crank arm is unlocked.
Assemble arms as shown with the gate in the
closed
position.
The elbow assembly’s flange
MUST
be on the
opposite side of the gate in the closed position.
This is
the physical stop used to set the open and close limits.
Concrete
Position
Gate Rail
Run all conduit on the opposite
side of the open gate.
Install gate
bracket to gate.
30” Crank Arm
60” Connecting Arm
Flange
Crank Power Arm
Elbow
Assembly
Point arms towards
gate bracket.
Gate Hinge Pivot Point
Arms MUST be level.
This distance can vary (6” minimum).
Varies
60” Connecting Arm
Gate
Bracket
26”
Conduit
2”
43”
Post Base
Open Gate
Closed Gate
90°
Depth of the concrete pad is
determined by soil conditions and
local building codes. Reinforced
concrete recommended.
Gate Bracket Height
Low
Volt
High
Volt
Inter
connection
Cable
Operator MUST
be level.
5”
12”
Note: 2” thick
gate Illustrated.
Concrete
Output Shaft