Commissioning
Operation
© 2007
27
3
Preparations for initial commissioning
(Maintenance schedule E 10)
z
Remove engine corrosion protection
z
Remove any transport devices.
z
Check the battery and cable connections and
mount if necessary.
z
Check belt tension (
53
).
z
Have the engine monitor or warning system
checked by authorised personnel.
z
Check the engine mounting.
z
Check that all hose unions and clips fit properly.
The following additional work must be carried
out on generally overhauled engines:
z
Check the fuel pre-filter and main filter and
change if necessary.
z
Check the intake air cleaner (if available, main-
tain according to maintenance indicator).
z
Fill with engine lube oil.
Fill with engine lube oil
z
Fill the engine with lubricating oil via the lubricat-
ing oil filler neck.
z
Observe the lubricating oil filling level (
70
).
z
Check lubricating oil level, if necessary top up.
Low lubricating oil level and overfilling lead
to engine damage.
The engines are generally supplied without
lubricating oil filling.
Select lubricating oil quality and viscosity
before filling.
Order DEUTZ lubricating oils from your
DEUTZ partner
Fill oil-bath air filter with lubricating oil
z
Fill lubricating oil pan (1) of the oil-bath filter with
lubricating oil as far as the marking arrow.
No lubricating oil may be filled in the cy-
clone pre-separator that may be connected
upstream.
OBJ_DOKU-12638-001.fm Seite 27 Mittwoch, 22. August 2007 9:25 09