3.
Attach the one-hole lug to the chassis using the supplied 10-32 screw with the captive internal tooth
lock washer. Torque the screw to 20 in-lbs.
Figure 8. Attaching the Ground Cable
a.
Lug hole
b.
Ground Screw
4.
Attach the other end of the ground cable to a suitable ground point. The rack installation ears are not
a suitable grounding point.
Installing the SFP+ and QSFP+ Optics
The S4810–ON has 48 SFP+ optical ports and four QSFP+ optical ports.
WARNING: ESD damage can occur if components are mishandled. Always wear an ESD-
preventive wrist or heel ground strap when handling the S4810–ON and its components.
WARNING: When working with optical fibers, follow all warning labels and always wear eye
protection. Never look directly into the end of a terminated or unterminated fiber or connector
as it may cause eye damage.
20
Install the S4810–ON
Содержание Networking S4810
Страница 1: ...Installing the S4810 System April 2014 ...
Страница 10: ... PSU status Fan tray status System Figure 3 S4810 ON LEDs 1 SYS 2 MASTER 3 FAN 4 PSU 10 The S4810 ON System ...
Страница 14: ...14 ...
Страница 30: ...30 ...
Страница 40: ...40 ...