Management network A, nodes 1 - 16 cabling
Use the following figure and table to connect cables for management network A, nodes 1 - 16.
Figure 21 Management A, nodes 1 - 16 cabling example
Node 16
Node 1
Mgmt Switch A
To core switch or
Mgmt Switch B
Mgmt Server
Data Switch A
Data Switch B
BMC/
iDRAC
2
4
MGMT1
NIC1
38
45
46
<…>
47
MGMT
48
Table 9 Management A, nodes 1 -16 cabling
Source
Destination
Node 1 BMC (iDRAC)
Management SwitchA Port 2
Node 1 MGMT1
Management SwitchA Port 4
Node 2 BMC (iDRAC)
Management SwitchA Port 6
Node 2 MGMT1
Management SwitchA Port 8
Node 3 BMC (iDRAC)
Management SwitchA Port 10
Node 3 MGMT1
Management SwitchA Port 12
Node 4 BMC (iDRAC)
Management SwitchA Port 14
Node 4 MGMT1
Management SwitchA Port 16
Install Management Network I/O Cables
Dell EMC VxFlex Ready Node Server Installation Guide
45
Содержание EMC VxFlex Ready Node
Страница 1: ...Dell EMC VxFlex Ready Node Server Installation Guide Rev 01 October 2019 ...
Страница 6: ...Figures 6 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 8: ...Tables 8 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 16: ...Before You Begin 16 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 18: ...R640 Procedures 18 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 56: ...R740XD Procedures 56 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 80: ...R840 Procedures 80 Dell EMC VxFlex Ready Node Server Installation Guide ...