Installation in cabinets with 3-phase wye power distribution
Note:
Install all the equipment in the cabinet before installing and connecting the
power and I/O cables.
l
Install the equipment as described in
Installation of the equipment in the
on page 20
.
l
If you are installing the minimum configuration, refer to the figure and table
below for minimum configurations for the equipment stack up in the cabinet.
l
If you are installing the maximum configuration, refer to the figure and table
below for maximum configurations for the equipment stack up in the cabinet.
Table 6 Minimum configuration in 3-phase wye power distribution cabinets
Component Function
Description
Quantity
Cabinet U Space
Data Server
R640 Server
3
2 - 4
Management Server
Management Server
1
20
Management Switch
Customer provided 1 GbE
switch
1
21
Data Switch
Customer provided 10 GbE
switch
2
23-24
R640 Equipment Installation
Dell EMC VxFlex Ready Node Server Installation Guide
27
Содержание EMC VxFlex Ready Node
Страница 1: ...Dell EMC VxFlex Ready Node Server Installation Guide Rev 01 October 2019 ...
Страница 6: ...Figures 6 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 8: ...Tables 8 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 16: ...Before You Begin 16 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 18: ...R640 Procedures 18 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 56: ...R740XD Procedures 56 Dell EMC VxFlex Ready Node Server Installation Guide ...
Страница 80: ...R840 Procedures 80 Dell EMC VxFlex Ready Node Server Installation Guide ...