CONTROL RACK INSTALLATION
USER MANUAL
15
Vertical installation
The control rack must be positioned in a safe manner, following the recommendations
below.
Figure 7: Control rack vertical positioning
Figure 8: Control rack fixing points for vertical installation
NOTE: The feet must be removed from the bottom of the control rack and
installed on the left side of the control rack using the appropriate fixing
points. Tightening torque = 0.5 Nm.
CAUTION: The control rack MUST be fixed to a side wall using the appropri-
ate fixing points placed on the bottom of the
control
rack.
Содержание AREX 401
Страница 1: ...AREX 401 USER MANUAL InfraRed Fiber Laser Marker...
Страница 66: ...SET UP 58 AREX 401 Figure 51 Connecting the monitor NOTE Minimum monitor resolution 800 x 600 VGA standard...
Страница 113: ...SLO INTEGRATION EXAMPLE USER MANUAL 105 SLO INTEGRATION EXAMPLE...
Страница 140: ...RECOVER THE LASER MARKER 132 AREX 401 Press FINISH to continue Press YES to continue...
Страница 141: ...HOW TO RECOVER THE LASER MARKER USER MANUAL 133 Wait for disks restoring The system will restart automatically...
Страница 145: ...USER MANUAL 137 APPENDIX G MECHANICAL DRAWINGS...
Страница 146: ...MECHANICAL DRAWINGS 138 AREX 401 CONTROL RACK NOTE Please refer to Datalogic website for detailed drawings...
Страница 147: ...SCAN HEAD USER MANUAL 139 SCAN HEAD NOTE Please refer to Datalogic website for detailed drawings...