FOR TECHNICAL QUESTIONS, CALL (877)432-6627
17
NOTE:
To ease installation of the top trough, it helps to
keep the anchor bolts loose on one of the columns
until the top trough is mounted.
STEP 5
(Install Powerside Column)
1. Before proceeding, double check measurements and make certain that the bases of each column are
square and aligned with the chalk line.
2. Using the base plate on the column as a guide, drill each anchor hole in the concrete approximately
4-1/2 deep using a rotary hammer drill and 3/4 concrete drill. To assure full holding power, do not
ream the hole or allow drill to wobble. (See figure 5 )
3. After drilling, remove dust thoroughly from each hole using compressed air and/or wire brush. Make
certain that the column remains aligned with the chalk line during this process.
4. Assemble the washers and nuts on the anchors then tap into each hole with a hammer until the washer
rests against the base plate. Be sure that if shimming is required that enough threads are left exposed.
( See figure 6 )
5. If shimming is required, insert the shims as necessary under the base plate so that when the anchor
bolts are tightened, the columns will be plumb. (See figure 7)
6. With the shims and anchor bolts in place, tighten by securing the nut to the base then turning 2-3 full
turns clockwise. DO NOT use an impact wrench for this procedure.
Drill hole
approximately 4-1/2
Deep.
Fig: 5
Tap anchor bolts into each hole
with a hammer until the washer
rests against the baseplate.
Fig: 6
Fig: 7