Model 9016 X-Purge Operator Interface
Daisy Data Displays, Inc.
February 2022
6
D010-000002
3
Pre-Installation Testing
Before installing your system in its final location, you may wish to test it to verify that the
purge system is functioning correctly.
3.1
Division 1 X-Purge Test
IMPORTANT NOTE:
Pre-installation testing should
always
be conducted in a safe area.
Equipment Required
•
Clean, dry purge air, or an inert gas supply equipped with local water/oil separator
or filter capable of supplying 40 to 300 SCFH at 30 to 60 PSI.
•
Fittings and tubing for purge air or inert gas supply (0.25” NPT Male to connect to
the inlet of the purge system).
•
Local air pressure shutoff valve.
•
120V, 8A or 240V, 4A AC power (w/ Ground) with pigtails, tinned bare wire and
stripped 0.25”
Procedure
1.
PLACE UNIT
in a safe area near a source of the purge gas to be used .
2.
Install pressure regulator
, along with a water/oil separator or filter, a shutoff
valve, a pressure relief valve, and a pressure gauge in the pressurized purge air (or
inert gas) line (see drawing P007).
3.
INPORTANT,
Bleed the pressurized purge air (or inert gas) line ensuring that any
dirt, moisture, and contaminants are cleared from the line before connecting the
pressurized purge air (or inert gas) line to the unit.
4.
Connect the purge gas line
to the inlet of the regulator on the Purge Unit.
5.
Remove cover
of the explosion-proof I/O casting (see drawing P007)
6.
Connect an AC power
line to the power interface board (see drawing P008). For
connection, location, and wiring, see drawing E017 (NOTE1).
7.
Close all access doors and covers
.
8.
Apply purge gas to the system
by opening the shutoff valve. Adjust pressure
regulator on the air-in box (see drawing P008) to 40 PSI.
9.
Apply AC power to the unit
.
10.
When pressure inside the unit reaches 1.0” WC and > 40 SCFH, the Purge Status
LED should illuminate yellow, indicating that it is purging.
IF THE INDICATOR DOES NOT ILLUMINATE
a thorough inspection for leakage of
the unit must be made. Panel gaskets can be checked with a soap solution. If
leaks are not visually apparent, verify that the pressurized air is clean, dry and is
40 PSI at the inlet.
DO NOT ATTEMPT TO OPEN THE ENCLOSURE WHILE IT IS PRESSURIZED!
OPENING PRESSURIZED ENCLOSURE CAN RESULT IN SERIOUS INJURY!
Содержание 9016 X-Purge
Страница 1: ...February 2022 D010 000002 Model 9016 X Purge User Manual...
Страница 19: ...Page 19...
Страница 20: ...Page 20...
Страница 21: ...Page 21...
Страница 22: ...Page 22...
Страница 23: ...Page 23...
Страница 24: ...Page 24...
Страница 25: ...Page 25...
Страница 26: ...Page 26...
Страница 27: ...Page 27...
Страница 28: ...Page 28...
Страница 29: ...Page 29...
Страница 30: ...Page 30...
Страница 32: ......
Страница 33: ......
Страница 34: ...Page 34...
Страница 35: ...Page 35...
Страница 36: ...Page 36...
Страница 37: ...Page 37...
Страница 38: ...Page 38...
Страница 39: ...Page 39...