18
|
Piping installation
Installer and user reference guide
92
RXYLQ10~14T7Y1B*
VRV IV system air conditioner
4P543427-1A – 2020.10
18.3.3 Checking refrigerant piping: Setup
p< p>
R410A
N2
C
b
c
e
a
g
f
d
A
B
a
Pressure reducing valve
b
Nitrogen
c
Weighing scales
d
Refrigerant R410A tank (siphon system)
e
Vacuum pump
f
Liquid line stop valve
g
Gas line stop valve
A
Valve A
B
Valve B
C
Valve C
Valve
State of valve
Valve A
Open
Valve B
Open
Valve C
Open
Liquid line stop valve
Close
Gas line stop valve
Close
NOTICE
The connections to the indoor units and all indoor units should also be leak and
vacuum tested. Keep any possible (field supplied) field piping valves open as well.
Refer to the indoor unit installation manual for more details. Leak test and vacuum
drying should be done before the power supply is set to the unit. If not, see also the
flow chart earlier described in this chapter (see
"About checking the refrigerant
18.3.4 To perform a leak test
The leak test must satisfy the specifications of EN378‑2.
To check for leaks: Vacuum leak test
1
Evacuate the system from the liquid and gas piping to –100.7 kPa (–1.007 bar)
(5 Torr absolute) for more than 2 hours.
2
Once reached, turn off the vacuum pump and check that the pressure does
not rise for at least 1 minute.
3
Should the pressure rise, the system may either contain moisture (see vacuum
drying below) or have leaks.
To check for leaks: Pressure leak test
1
Test for leaks by applying a bubble test solution to all piping connections.
2
Discharge all nitrogen gas.
3
Break the vacuum by pressurising with nitrogen gas to a minimum gauge
pressure of 0.2 MPa (2 bar). Never set the gauge pressure higher than the
maximum operation pressure of the unit, i.e. 4.0 MPa (40 bar).