8 Commissioning
Installer reference guide
19
FTXTA30A2V1BW
Split system air conditioner
4P518023-6E – 2019.04
a
a
Address jumper J4
NOTICE
Be careful NOT to damage any of the surrounding parts
when cutting the address jumper.
3
Turn the power supply on.
4
Press
and
simultaneously.
5
Press
, select and press
.
Result:
The operation lamp will start to blink.
a
a
Indoor unit ON/OFF switch and operation lamp
6
Press the indoor unit ON/OFF switch while the operation lamp
is blinking.
Address jumper
Address
Factory setting
1
After cutting with nippers
2
INFORMATION
If the setting could NOT be completed while the operation
lamp was blinking, repeat the setting process from the
beginning.
7
When the setting is complete, keep
pressed for at least
5 seconds.
Result:
The user interface will return to the previous screen.
8
Commissioning
8.1
Overview: Commissioning
This chapter describes what you have to do and know to
commission the system after it is installed.
Typical workflow
Commissioning typically consists of the following stages:
1
Checking the "Checklist before commissioning".
2
Performing a test run for the system.
8.2
Checklist before commissioning
After the installation of the unit, first check the following items. Once
all below checks are fulfilled, the unit MUST be closed, ONLY then
can the unit be powered up.
You read the complete installation instructions, as
described in the
installer reference guide
.
The
indoor units
are properly mounted.
The
outdoor unit
is properly mounted.
Air inlet/outlet
Check that the air inlet and outlet of the unit is NOT
obstructed by paper sheets, cardboard, or any other
material.
There are NO
missing phases
or
reversed phases
.
The
refrigerant pipes
(gas and liquid) are thermally
insulated.
Drainage
Make sure drainage flows smoothly.
Possible consequence:
Condensate water might drip.
The system is properly
earthed
and the earth terminals
are tightened.
The
fuses
or locally installed protection devices are
installed according to this document, and have NOT been
bypassed.
The
power supply voltage
matches the voltage on the
identification label of the unit.
The specified wires are used for the
interconnection
cable
.
The indoor unit receives the signals of the
user interface
.
There are NO
loose connections
or damaged electrical
components in the switch box.
The
insulation resistance
of the compressor is OK.
There are NO
damaged components
or
squeezed
pipes
on the inside of the indoor and outdoor units.
There are NO
refrigerant leaks
.
The correct pipe size is installed and the
pipes
are
properly insulated.
The
stop valves
(gas and liquid) on the outdoor unit are
fully open.
8.3
To perform a test run
Prerequisite:
Power supply MUST be in the specified range.
Prerequisite:
Test run may be performed in cooling or heating
mode.
Prerequisite:
Test run should be performed in accordance with the
operation manual of the indoor unit to make sure that all functions
and parts are working properly.
1
In cooling mode, select the lowest programmable temperature.
In heating mode, select the highest programmable temperature.
Test run can be disabled if necessary.
2
When the test run is finished, set the temperature to a normal
level. In cooling mode: 26~28°C, in heating mode: 20~24°C.
3
The system stops operating 3 minutes after the unit is turned
OFF.