6 Commissioning

Installation manual

22

EHBH/X04+08DA*V7

Daikin Altherma 3 R W

4P618951-1 – 2020.03

6

Commissioning

NOTICE

ALWAYS operate the unit with thermistors and/or pressure
sensors/switches. If NOT, burning of the compressor might
be the result.

INFORMATION

Protective  functions  –  "Installer-on-site  mode".

  The

software  is  equipped  with  protective  functions,  such  as
room antifrost. The unit automatically runs these functions
when necessary.

During  installation  or  service  this  behaviour  is  undesired.
Therefore, the protective functions can be disabled:

At  first  power-on:

  The  protective  functions  are

disabled by default. After 36 h they will be automatically
enabled.

Afterwards:

  An  installer  can  manually  disable  the

protective  functions  by  setting  [9.G]: 

Disable

protections

=

Yes

.  After  his  work  is  done,  he  can

enable  the  protective  functions  by  setting  [9.G]:

Disable protections

=

No

.

6.1

Checklist before commissioning

After  the  installation  of  the  unit,  first  check  the  items  listed  below.
Once all checks are fulfilled, the unit must be closed. Power-up the
unit after it is closed.

You  read  the  complete  installation  instructions,  as
described in the 

installer reference guide

.

The 

indoor unit

 is properly mounted.

The 

outdoor unit

 is properly mounted.

The following 

field wiring

 has been carried out according

to this document and the applicable legislation:

▪ Between the local supply panel and the outdoor unit

▪ Between indoor unit and outdoor unit

▪ Between the local supply panel and the indoor unit

▪ Between the indoor unit and the valves (if applicable)

▪ Between  the  indoor  unit  and  the  room  thermostat  (if

applicable)

▪ Between  the  indoor  unit  and  the  domestic  hot  water

tank (if applicable)

The  system  is  properly 

earthed

  and  the  earth  terminals

are tightened.

The 

fuses

  or  locally  installed  protection  devices  are

installed according to this document, and have NOT been
bypassed.

The 

power  supply  voltage

  matches  the  voltage  on  the

identification label of the unit.

There  are  NO 

loose  connections

  or  damaged  electrical

components in the switch box.

There  are  NO 

damaged  components

  or 

squeezed

pipes

 on the inside of the indoor and outdoor units.

Backup  heater  circuit  breaker

  F1B  (field  supply)  is

turned ON.

Only for tanks with built-in booster heater:

Booster  heater  circuit  breaker

  F2B  (field  supply)  is

turned ON.

There are NO 

refrigerant leaks

.

The 

refrigerant  pipes

  (gas  and  liquid)  are  thermally

insulated.

The  correct  pipe  size  is  installed  and  the 

pipes

  are

properly insulated.

There is NO 

water leak

 inside the indoor unit.

The 

shut-off valves

 are properly installed and fully open.

The 

stop valves

 (gas and liquid) on the outdoor unit are

fully open.

The 

air purge

 valve is open (at least 2 turns).

The 

pressure  relief  valve

  purges  water  when  opened.

Clean water must come out.

The 

minimum  water  volume

  is  guaranteed  in  all

conditions. See "To check the water volume and flow rate"
in 

"3.2 Preparing water piping" 

[

4

 6].

(if  applicable)  The 

domestic  hot  water  tank

  is  filled

completely.

6.2

Checklist during commissioning

The 

minimum  flow  rate

  during  backup  heater/defrost

operation  is  guaranteed  in  all  conditions.  See  "To  check
the  water  volume  and  flow  rate"  in 

"3.2  Preparing  water

piping" 

[

4

 6].

To perform an 

air purge

.

To perform a 

test run

.

To perform an 

actuator test run

.

Underfloor screed dryout function

The  underfloor  screed  dryout  function  is  started  (if
necessary).

6.2.1

To check the minimum flow rate

1

Check the hydraulic configuration to find out which
space heating loops can be closed by mechanical,
electronic, or other valves.

2

Close all space heating loops that can be closed.

3

Start the pump test run (see 

"6.2.4 To perform an

actuator test run" 

[

4

 23]).

4

Read out the flow rate

(a)

 and modify the bypass valve

setting to reach the minimum required flow rate + 2 l/
min.

(a)

During pump test run, the unit can operate below the minimum
required flow rate.

Minimum required flow rate

12 l/min

6.2.2

To perform an air purge

Conditions: 

Make  sure  all  operation  is  disabled.  Go  to  [C]:

Operation

  and  turn  off 

Room

Space  heating/cooling

  and 

Tank

operation.

Содержание EHBH08DA6V7

Страница 1: ...Installation manual Daikin Altherma 3 R W English Installation manual Daikin Altherma 3 R W EHBH04DA6V7 EHBH08DA6V7 EHBH08DA9W7 EHBX04DA6V7 EHBX08DA6V7 EHBX08DA9W7...

Страница 2: ...u s na imi pokyny odpov daj n sleduj c m norm m nebo normativn m dokument m u skladu sa slijede im standardom ima ili drugim normativnim dokumentom ima uz uvjet da se oni koriste u skladu s na im uput...

Страница 3: ...izard Main zone 17 5 2 6 Configuration wizard Additional zone 17 5 2 7 Detailed screen with weather dependent curve 18 5 2 8 Configuration wizard Tank 19 5 3 Settings menu 20 5 3 1 Main zone 20 5 3 2...

Страница 4: ...es Space heating operation 5 30 C Space cooling operation 5 35 C Domestic hot water production 5 35 C Mind the following spacing installation guidelines H 1150 200 200 500 mm 450 H Height measured fro...

Страница 5: ...ate the minimum opening area for natural ventilation between room A and room B VAmin cm2 Unit can be installed at room A if 2 ventilation openings permanently open are provided between room A and B 1...

Страница 6: ...ernal actuators Item Description Wires Maximum running current Outdoor unit and indoor unit power supply 1 Power supply for outdoor unit 2 GND a 2 Power supply and interconnection cable to indoor unit...

Страница 7: ...witch box cover 4 3 If you have to do work behind the switch box open the switch box 2 1 2 4 If you have to do work behind the user interface panel or upload new software into the user interface open...

Страница 8: ...2 2 To connect the drain hose to the drain Water coming from the pressure relief valve is collected in the drain pan You must connect the drain pan to an appropriate drain according to the applicable...

Страница 9: ...of maximum 10 bar 1 MPa must be installed on the domestic cold water inlet connection in accordance with the applicable legislation 4 4 2 To fill the water circuit To fill the water circuit use a fiel...

Страница 10: ...3 6 a Interconnection cable main power supply b Normal kWh rate power supply c Preferential power supply contact 2 Fix the cables with cable ties to the cable tie mountings INFORMATION In case of pre...

Страница 11: ...ace point between the user s supply and the public system It is the responsibility of the installer or user of the equipment to ensure by consultation with the distribution network operator if necessa...

Страница 12: ...case of an electricity meter with transistor output check the polarity The positive polarity MUST be connected to X5M 6 and X5M 4 the negative polarity to X5M 5 and X5M 3 1 Connect the electricity me...

Страница 13: ...stat normally closed cable to the appropriate terminals as shown in the illustration below X5M 9 10 2 Fix the cable with cable ties to the cable tie mountings NOTICE Make sure to select and install th...

Страница 14: ...You can access the installer settings using two different methods However NOT all settings are accessible via both methods If so the corresponding table columns in this chapter are set to N A not appl...

Страница 15: ...t in backup heater the type of heater can be viewed but not changed Code Description 9 3 1 E 03 2 3V 3 6V 4 9W Domestic hot water The following setting determines if the system can prepare domestic ho...

Страница 16: ...thermostatic valve to avoid too high temperatures towards a low temperature emitter Make sure you set the emitter types for the main zone 2 7 and for the additional zone 3 7 correctly in accordance w...

Страница 17: ...Enable leaving water temperature modulation and increase the maximum modulation 2 C Control Define how the operation of the unit is controlled Control In this control Leaving water Unit operation is d...

Страница 18: ...ecrease the temperature of the leaving water for different ambient temperatures For example if leaving water temperature is in general fine but at low ambient temperatures too cold raise the slope so...

Страница 19: ...Domestic hot water tank 5 2 8 Configuration wizard Tank This part only applies to systems with an optional domestic hot water tank installed Heat up mode The domestic hot water can be prepared in 3 di...

Страница 20: ...ou can set additional settings using the main menu screen and its submenus The most important settings are presented here 5 3 1 Main zone Thermostat type Only applicable in external room thermostat co...

Страница 21: ...ilibrium temperature Operation 9 4 Booster heater Capacity BSH allowance schedule BSH eco timer Operation 9 6 Balancing Space heating priority Priority temperature Offset BSH setpoint Minimum running...

Страница 22: ...age on the identification label of the unit There are NO loose connections or damaged electrical components in the switch box There are NO damaged components or squeezed pipes on the inside of the ind...

Страница 23: ...test run the correct operation of the unit can be checked by monitoring its leaving water temperature heating cooling mode and tank temperature domestic hot water mode To monitor the temperatures 1 In...

Страница 24: ...ult in cracking of the screed NOTICE For the underfloor heating screed dryout to be able to start make sure the following settings are met 4 00 1 C 02 0 D 01 0 4 08 0 4 01 1 7 Hand over to the user On...

Страница 25: ...ing water IN a2 Space heating water OUT b1 Gas refrigerant IN heating mode condenser b2 Liquid refrigerant OUT heating mode condenser c1 Liquid refrigerant IN cooling mode evaporator c2 Gas refrigeran...

Страница 26: ...wired On OFF thermostat wired On OFF thermostat wireless On OFF thermostat wireless Ext thermistor External thermistor Heat pump convector Heat pump convector Position in switch box English Translati...

Страница 27: ...witch box 5 Ext thermistor 5 External thermistor SWB Switch box English Translation 6 Field supplied options 6 Field supplied options 12 V DC pulse detection voltage supplied by PCB 12 V DC pulse dete...

Страница 28: ...mostat A13P P1 P2 LAN adapter A14P P1 P2 user interface Optional parts Optional parts External room thermostat Heat pump convector main and or additional zone 5 core for C H operation 4 core for H onl...

Страница 29: ...H 1150 200 200 500 mm 450 8 4 Table 2 Minimum floor area indoor unit mc kg Minimum floor area m H 1150 mm H 1200 mm H 1300 mm H 1400 mm H 1500 mm H 1600 mm H 1700 mm H 1800 mm 1 84 8 57 7 84 6 64 5 92...

Страница 30: ...when H is between two H values from the table consider the value that corresponds to the lower H value from the table If H 1450 mm consider the floor area that corresponds to H 1400 mm For intermediat...

Страница 31: ......

Страница 32: ...4P618951 1 2020 03 Copyright 2020 Daikin 4P618951 1 0000000S Verantwortung f r Energie und Umwelt...

Отзывы: