4 Installation
Installation manual
10
D2CND024A1/4AB + D2TND012~024A4AB
Wall-mounted condensing boiler
3P469346-3N – 2019.11
a
a
Vertical, flat wall
▪ The boiler can be installed outdoors in a partially protected
location. A partially protected location is a place where the boiler
is not exposed to the direct action and to the penetration of
atmospheric precipitation (rain, snow, hail,...).
The boiler can also be installed inside of an outside wall using the
appropriate in‑wall kit.
In case of outdoor installation, use the antifreeze kit
(DRANTIFREEZxx ) to prevent the piping and condensate trap
from freezing.
▪ Flammable fluids and materials must be stored at least 1 metre
away from the boiler.
▪ The wall on which the unit is mounted should be strong enough to
carry the unit's weight. Build a reinforcement if necessary.
▪ The following minimum clearances are required for servicing:
180 mm above the casing*, 200 mm below, and 10 mm at each
side. 500 mm at the front clearance may be realised by opening a
cupboard door. See
"Minimum installation clearances"
10].
▪ For easier use of control panel, it is recommended that boiler
bottom is 1500 mm from the floor, for easier part replacement side
clearances should be 50 mm where applicable. See
10].
▪ If the boiler is installed in a room or compartment, it does not
require a dedicated ventilation for combustion air. If however
installed in a room containing a bath or a shower, then particular
reference is drawn to the current I.E.E. Wiring Regulations, local
Building Regulations or any other local regulations currently in
service.
▪ The intake air must not include chemicals that may cause
corrosion, toxic gas formation and even risk of explosion.
▪ If the wall on which the unit is mounted, is flammable, a non-
flammable material must be placed between the wall and the unit
and also at all locations through where the flue piping passes.
Minimum installation clearances
a
a
d
f
c
e
d
b
Minimum allowable clearances
a, sides
10 mm
b, Above the casing*
180 mm
c, below
200 mm
f, in front
500 mm
Recommended clearances for easy servicing
d, sides
50 mm
e, below (from the floor)
1500 mm
*
180 mm
is for the case that 60/100 90° elbow is connected
to the flue outlet of the boiler.
b = 270 mm
in case that 60/100 to 80/80 a 90°
elbow 80 are connected to the flue outlet of the boiler.
b = 280 mm
in case that 60/100 to 80/125 a 90°
elbow 80/125 are connected to the flue outlet of the boiler.
4.3
To unpack the unit
1
Unpack the unit as shown on top of the packing case. The
following items must be included in the package:
a
b
c
d
e
f
g
h
i
j
a
Combi boiler
b
Operation manual
c
Installation manual
d
Wall-mounting bracket
e
Installation template
f
Dowels and screws
g
Condensate hose
h
Cable glands 2×PG 7, 1×PG 9
i
Energy label
j
Storage tank temperature sensor (only for models
D2TND012A4AB, D2TND018A4AB and D2TND024A4AB)
2
Check the contents of the package. If any of them is damaged
or missing, contact your dealer.
CAUTION
Store the remaining parts of the package (cardboard,