PROGRAMMING THE MOTOR

 

The motor must be programmed in order that the gate operate correctly. Once programming is com­ 
plete, the program is held in the memory on the microchip and there is no need to re­program the motor 
after the initial program. 
It is important to note that the following points should be checked before the gate is programmed.

 

·

Gear box is filled with the gearbox oil.

 

·

Motor is level.

 

·

Rack is secure to the gate and engaged with the pinion gear.

 

·

The gate has adequate end stops. (

DO NOT

 automate a gate without end stops)

·

The gate must run freely and not jam at

 ANY

 point in its travel.

 

·

The magnet is mounted correctly.

TO PROGRAM THE MOTOR

Ensure that

 all power

 is removed from the board. 

The LCD screen is designed to assist with the programming of the motor.

 

Step 1

: manually open the gate 1m ­1.5m. 

Step 2

: engage the motor using the thumb wheel.

 

Step 3

have dip switch 1 & 2 in the 'ON' position

 

Step 4

: apply the battery power. The three LED’s will flash rapidly. 

T

he LCD will say 

“ PROGRAM MODE ­ PRESS BUTTON”

 

Step 

5

: press the TEST button on the PC board. The gate will automatically do the following: 

a)

Close

 slowly until the end stop is struck

b)

Open

 slowly until the end stop is struck.

Step 7

: after closing it will automatically re­open. 

Now the LCD screen will say 'PUT SW 1 OFF' 

The 

motor is now fully programmed and ready for normal use. 

In

 Step 6

 the gate must close after triggering the motor. If  the gate opens instead it indicates that the

 

motor wires

 need to be reversed. This will change the motor direction. {See Setting the motor direction}

 

Do not

 connect any auxiliary wires to the board until the motor is fully programmed.

Содержание SPRINT

Страница 1: ...P9 ANCHORING THE MOTOR P11 SECURING THE MOTOR P12 MOUNTING THE RACK P13 FILLING THE GEARBOX OIL P14 MOUNTING THE MAGNET P14 MAIN PC BOARD LAYOUT P15 LCD SCREEN P16 SETTING THE MOTOR DIRECTION P17 PROG...

Страница 2: ...nding BMG Imports offer a Standard Warranty on this equipment The following terms and conditions apply to ALL warranty claims BMG Imports warrants the ORIGINAL purchaser at the point of sale that the...

Страница 3: ...no circumstances may 220V AC be run using Communication cable Ripcord or Cabtyre BMG Imports will not be held liable for any accident incident resulting in damage injury or death ensuing from the inst...

Страница 4: ...ckle charge to maintain 13 8 VDC charge to the battery Main PC board this is the printed circuit board that contains all the electronic components that oper ate the motor NOTE Always remove the power...

Страница 5: ...5 MOTOR LAY OUT 4 HOLES TO PEG OR BOLT THE PLATE CONDUIT ENTRY HOLES FOUNDATION PLATE 12VOLT DC ELECTRIC MOTOR MAIN PC BOARD CABLE RISERS 12 VOLT BATTERY ACCESS DOOR WITH LOCK L C D SCREEN...

Страница 6: ...to avoid any damage to the motor The rail must be level and should be above ground level this will assist with keeping debris out of the path of the wheels Any debris lying on the rail may cause the...

Страница 7: ...assist with the smooth operation of the gate The gate must not move on its own when left in any position on the rail D A C E will not be held responsible for any gates bumping the ends stops when a ga...

Страница 8: ...equired to start the gate rolling This is the start up force At no stage while moving the gate must the reading exceed the force shown in the table below START UP FORCE Start up force table Sprint max...

Страница 9: ...MANUAL OVER RIDE PLACING MOTOR INTO MANUAL OVER RIDE Open the door as in step 1 above Turn the thumb wheel CLOCKWISE until the gate moves freely PLACING THE MOTOR IN NORMAL OPERATION MODE Turn the th...

Страница 10: ...ter proof conduit and must be terminated inside the motor There must be no joins in the cable underground The cable should be a two core 1 5mm cable DO NOT USE COMMUNICATION CABLE AS THIS WILL VOID AN...

Страница 11: ...e The concrete should be allowed sufficient time to set before the mo tor is mounted onto the plate Allow concrete to set and then place the foundation plate onto the concrete plinth 3 Foundation plat...

Страница 12: ...bove the flood level or if this is not possible a flood proof wall should be constructed around the motor After placing the motor onto the three jack up bolts place the three clamping nuts and washers...

Страница 13: ...B Step 4 push the gate towards the open position continuing to secure the rack to the full length of the gate Ensure that the rack is securely meshed with the pinion at all times during this operatio...

Страница 14: ...ses the motor must not exceed 3mm To check this manually move the gate until the magnet is directly over the pinion gear then measure be tween the magnet and the motor lid If the gap is more than 3mm...

Страница 15: ...according to the instructions in this manual It is very important to remember to disconnect ALL power before connecting or discon necting any wiring MAIN P C BOARD LAY OUT LED extension con nector Re...

Страница 16: ...THE CLOSED POSITION GATE OPEN THE GATE IS IN THE OPEN POSITION OBSTRUCTION THE GATE HAS SENSED AN OBSTRUCTION CHECK THE WHEELS ROLLERS RACK BRACKETS FUSES FORCE SETTING POTS AUTO CLOSE ACTIVE THE GAT...

Страница 17: ...The motor wires are the two wires that extend from the electric motor and are connected to the main PC board The other reason that the setting of the motor direction is important is that the motor wi...

Страница 18: ...is designed to assist with the programming of the motor Step 1 manually open the gate 1m 1 5m Step 2 engage the motor using the thumb wheel Step 3 have dip switch 1 2 in the ON position Step 4 apply t...

Страница 19: ...afe storage It is recommended that the remotes are numbered in order of programming This will assist with erasing any lost or stolen remote at a later stage Step 1 place the jumper over the two pins o...

Страница 20: ...OSE Auto close is an option that allows the gate to close automatically after a chosen time delay this delay can be from 10 to 70 seconds Auto close is selected by using the dipswitches on the main PC...

Страница 21: ...1m Collision Sensing Electronic Electronic Duty Cycle 20 20 Motor Voltage 12 Volt 12 Volt Motor Power 120 watts 120 watts Opening Time 25m min 18m min Supply Voltage at Gate 16V AC 16V AC On board rec...

Отзывы: