10
(2) When warmed or at the high temperature, the air door of engine should be switched to
start position
7.5. Turn the switch of engine to “start” position
7.6. The pre-warning time should be 3-5mins
Notice: speed is adjusted in place before shipment. Do not adjust at will, which
will cause engine rotation speed quicker or slower.
8. Starting Procedure
8.1. Process pre-starting procedure 7.1 to 7.6 completely
。
8.2. Switch the air door to” on”
。
8.3. Connect loading at normal loading ranges and check the voltage
9. Stop Procedure
9.1. Closing loading process so as to keep the machine at no-load status.
9.2. Switch the engine to “stop” position
9.3. Shut down the fuel switch
10. Welder, generator operation
10.1. Prepare machine and all relative work.
10.2. Choose correct welding cable and connect the power supply. Connecting lug and
terminal must be reliable in case of poor contact burning. Cable diameter should
match the standard 5~7A/mm
2
current flow.
10.3. Keep good ventilation; do not put other things on the machine so as to avoid any
negative influence to heat elimination.
10.4. Choose correct welding electrode according to work piece thickness.
10.5. Start machine step by step according the Operator Manual. After 5 minutes stable
running under no load status to heat engine, then start welding or power outlet.
10.6. Welding current should be adjusted according work piece thickness and electrode.
There is welding adjusting knob.
10.7. Welding current for different electrode diameter
Table
(
2
)
Welding Dia.(mm)
2.0
2.5
3.2
4.0
Welding current
(
A
)
50-65 60-80
100-130
140-190