3. Test wiring for correctness with continuity checks and also for unwanted grounds with

insulation resistance tester.

4. Allow the ELPS to charge under line power for 72 hours before initiating any testing of

the emergency operation of the lights.

D. Complete Installation

1. Install CID101 corrosion inhibitor device (supplied loose in ELPS50). Recommended

location is on the bottom wall between “Main Power On” pilot light and 1" NPT tapped

hole. Refer to CID101 instructions for installation.

2. Close cover and securely tighten all cover bolts and nuts to 30 ft. lbs. torque making

certain that no cover bolts are omitted.   Use only bolts supplied with the enclosure. 

NOTE:

ELPS units have two stud bolts located at diagonally opposite corners of the

body to aid in positioning cover.

DO NOT

depress the push-to-test pushbutton until after the ELPS has been powered

for 72 hours.  The emergency battery requires 72 hours to fully charge.  The indicating

light will illuminate steadily (no pulsing) when the ELPS is fully charged.

3. Test emergency lighting system for proper operation:

a. Turn on power to designated disconnect switch.

b. Turn on designated disconnect switch and observe:

“Main Power ON” indicating pilot light should be operating.

EVLA12 emergency light(s) should be “OFF”.

c. Press “Push-to-Test” indicating push button switch and observe:

“Main Power ON” light should be “OFF”.

EVLA12 emergency light(s) should be “ON”.

4. Lock designated disconnect switch “ON” to prevent unauthorized persons from turning

system “OFF”.

5. Adjust EVLA12 emergency light(s) for the desired direction of illumination & lock into

position using 1-5/8” open-ended wrench & torquing to 58 lb.-ft.  See Figure 2.

E.  Remote Mounting EVLA12 Emergency Light Only

1.   Attach the EVLA12 to a Cooper Crouse-Hinds EABC36 or EABL36 1" NPT outlet box.

2.   Secure this assembly to the mounting surface with ¼ inch bolts or lag screws of the

required length (not supplied).

3. Refer to Table 1 on page 6 for conductor recommendations.

4.  Refer to Sections B for aiming adjustments and section C for Conduit Connections and

Wiring.

PERIODIC TESTING

Article 700 of the National Electrical Code states that, “Systems shall be tested

periodically on a schedule acceptable to the authority having jurisdiction to assure their

maintenance in proper operating condition”. It also states that, “A written record shall be

kept of such tests and maintenance”.

In the absence of periodic testing requirements by a local authority, the following

recommendations from the NFPA 101 (2003) Life Safety Code are strongly recommended:

1.

Monthly

: Operate “Push-to-Test” switch and keep depressed for a minimum of 30

seconds. Observe that emergency lighting fixtures are on full brightness for the full

time. Record the test on the maintenance record card. Maintenance Record Card is

provided in instruction sheet envelope.

2.

Annually:

Shut off power at the distribution panel. Verify that the emergency lighting

fixtures remain “ON” for a minimum of 1-1/2 hours. 

NOTE: 

Leave the designated disconnect switch “ON” during this test so that battery

circuit is not interrupted. We suggest that this test be continued until the power supply

automatically shuts the emergency light(s) off. This will help maintain full battery

capacity.

Record the test on the Maintenance Record Card.

Allow 48 hours charging time before depending on the battery to operate at full

capacity.

Failure to function properly in either test may indicate the need for battery or lamp

replacement.

IF 1510  •  05/06

Copyright © 2006, Cooper Industries, Inc.

Page 4

Figure 5.  ELPS50 Controls

CAUTION

To avoid explosion, clean both flat joint surfaces of body and cover before closing.
Dirt or foreign material must not accumulate on flat joint surfaces. Surfaces must
seat fully against each other to provide a proper explosion proof seal.

WARNING

To avoid electrical shocks, use fixture only on systems with an equipment
grounding conductor.

NOTE

Unit needs to charge for 72 hours before conducting any tests.  Do not disconnect
AC power until unit is fully charged.

NOTE

In Class II and Class III and Simultaneous Presence locations, limit upward
aiming of fixture to a maximum of 30º above horizontal. Greater upward aiming
could lead to excessive dust buildup and dangerous overheating of the dust.

NOTE

A Class I, Division 1 sealing fitting must be installed within 18 inches of the
conduit entry of the ELPS enclosure.  Use Chico A or Chico SpeedSeal sealing
compound to seal the conduit entry.

Содержание ELPS50

Страница 1: ...included with all fixtures The EVLA12 is suitable for NEMA 4X locations when remote mounted not installed on an ELPS Power Supply and supplied with a NEMA 4X breather drain NOTE Ambient temperature at...

Страница 2: ...sen Nut A position lamp head in desired vertical position and retighten to 58 lb ft torque 4 Using the same 1 5 8 wrench loosen Nut B and position lamp head in desired horizontal position Be sure to r...

Страница 3: ...VAC primary through designated disconnect to terminal 120 3 Connect 220 240 VAC primary through designated disconnect to terminal 220 240 4 Connect 277 VAC primary through designated disconnect to te...

Страница 4: ...tates that Systems shall be tested periodically on a schedule acceptable to the authority having jurisdiction to assure their maintenance in proper operating condition It also states that A written re...

Страница 5: ...stall lens ring by turning clockwise until threads are fully engaged All screw threads have been treated with a corrosion resistant lubricant Whenever disturbing threaded joints relubricate the thread...

Страница 6: ...GRD 1 through L 7 6 Remove the mounting stud and pillar located in the uppermost left corner of the interior Remove the three other hold down nuts and lock washers on the aluminum backplate Remove the...

Страница 7: ...ch and observe Main Power ON light should be OFF and the EVLA12 emergency light s should be ON 6 Lock the Designated disconnect switch ON to prevent unauthorized persons from turning system OFF 7 Cond...

Страница 8: ...LATION AND MAINTENANCE INSTRUCTION SHEETS FOR METHODS OF TESTING All statements technical information and recommendations contained herein are based on information and tests we believe to be reliable...

Страница 9: ...ts de normes NEMA 4X lorsque install distance n utilise pas un bloc d alimentation ELPS et fourni avec un reniflard purge REMARQUE pour maximiser la dur e de fonctionnement du bloc d alimentation ELPS...

Страница 10: ...8 po desserrer l crou A positionner la t te du luminaire dans la position verticale voulue et resserrer l crou un couple de 58 lb pi 4 Utiliser la m me cl de 1 5 8 po desserrer l crou B et positionne...

Страница 11: ...ivre le c blage de l alimentation EDS2129 EDS2129GB pour les applications de groupe B interrupteur sectionneur d sign pour installation distance non fourni Installer selon les directives fournies avec...

Страница 12: ...s devraient tre test s r guli rement selon un programme acceptable par les autorit s qui ont juridiction pour assurer un bon tat de fonctionnement continuel Elle pr cise galement qu un registre par cr...

Страница 13: ...de la lentille La tourner dans le sens horaire pour visser compl tement tout le filetage Tous les filets de la vis ont t enduits d un lubrifiant r sistant la corrosion D s qu un joint filet est manipu...

Страница 14: ...n 3 Apr s avoir coup toutes les sources d alimentation du luminaire retirer toutes les attaches du couvercle pour acc der aux l ments internes 4 D brancher les fils de la lampe t moin et de l interrup...

Страница 15: ...t moin Main Power ON alimentation principale pr sente devrait tre TEINTE et l clairage de s curit EVLA12 devrait FONCTIONNER 6 Verrouiller l interrupteur sectionneur d sign en position ON marche pour...

Страница 16: ...DE DIRECTIVES D INSTALLATION ET D ENTRETIEN POUR CONNA TRE LES M THODES D ESSAI Toutes les d clarations tous les renseignements techniques et toutes les recommandations dans les pr sentes sont bas s...

Страница 17: ...cesorios incluyen l mparas El EVLA12 est dise ado para reas NEMA 4X cuando se monta remotamente no se instala sobre una fuente de alimentaci n ELPS y se suministra con un respiradero drenaje NEMA 4X N...

Страница 18: ...a llave de 1 5 8 afloje la Tuerca A coloque la cabeza de la l mpara en la posici n vertical deseada y apriete a 58 lb ft de torque 4 Con la misma llave de 1 5 8 afloje la Tuerca B y coloque la cabeza...

Страница 19: ...GB para aplicaciones Grupo B Interruptor con montaje remoto no suministrado Instale seg n las instrucciones suministradas con el interruptor EDS2129 GB Realice el cableado a los terminales 8 y 9 Vea e...

Страница 20: ...dicamente seg n un cronograma aceptable para las autoridades con jurisdicci n para garantizar su mantenimiento en condiciones de operaci n adecuadas Tambi n indica que se debe mantener un registro es...

Страница 21: ...en Halogen G4 2 pins 14 watts 6 Instale el anillo de la lente girando en el sentido de las agujas del reloj hasta enroscarlo por completo Todas las cuerdas de los tornillos fueron tratadas con un lubr...

Страница 22: ...tapa para acceder al interior 4 Desconecte las puntas de los cables en la l mpara piloto y el interruptor 5 Desconecte todas las conexiones entrantes de los terminales GRD 1 a L 7 6 Retire el perno de...

Страница 23: ...r an estar encendidas 6 Configure el interruptor de desconexi n designado en ON para evitar que personas no autorizadas apaguen el sistema 7 Realice pruebas peri dicas de acuerdo con el Manual de Inst...

Страница 24: ...EEMPLAZO DE L MPARA NOTAS HORA BATER A POR INDICAR UBICACI N DEL ACCESORIO DURACI N DE LA PRUEBA REGISTRO DE MANTENIMIENTO REQUISITOS NFPA 101 2003 SE DEBE REALIZAR UNA PRUEBA FUNCIONAL SOBRE TODOS LO...

Отзывы: