8.1.2
Place appropriate grommet onto buffer tube. If more than one buffer tube, both may be installed into one
grommet.
8.1.3
Insert into routing tray, sliding grommet to align with retaining groove in routing tray.
8.1.4
Secure with cable tie. See photos 95-100.
Standard LBT Micro Grommet LBT
Photo 95
Photo 96
Photo 97
Photo 98
Photo 99
Photo 100
8.1.5
Repeat steps 8.1.1 to 8.1.4 with buffer tube coming from other end of cable.
8.1.6
Route express fibers and fibers cut “dead to field” to the Feed Thru tray. See photo 101
Photo 101
8.1.7
Route fiber(s) to be spliced to top tray. See photos 102-104.