Installation of the ADU (60 cm)
98-175666-A
Chapter 2: Installation
2-25
2.4.1 To install the ADU
Prerequisites
• Ensure that the crane hook has a closing mechanism to prevent accidental slippage of
the lifting straps.
• Check for potential interference, read more in
Interference from radar, GPS/GNSS, L-
• Install the ADU at a location where
vibrations are limited to a minimum
.
•
Important
:
Maintain the vertical orientation of the ADU center line
.
• Always use
all 4 bolts
when installing the ADU.
You do not need to align the ADU with the bow-to-stern line of the ship. When configuring
the SAILOR XTR Ka you make an automated azimuth calibration to obtain the correct
azimuth of the ADU.
Installation procedure
To install the ADU, do as follows:
1. Install the mast with the mast flange and have the 4 M1210 bolts ready.
2. Open the ADU cardboard packaging.
3. Remove the foam protection layer at the top.
4. Take the 4 lifting straps and connect them to the crane hook.
5. Attach two tag lines of suitable length to the harness and man them.
6. With a crane lift the ADU off the packaging and move it on top of the mast. Maintain
vertical orientation of the ADU center line
.
Figure 2-28: ADU installation, 4 lifting straps on crane hook