The universal tire-changer must be installed on a levelled concrete floor at least 8” (20 cm.) thick, with a minimum concrete quality of
B25 in accordance with DIN 1045 requirements (foundations).
For your reference see the side drawing as well as the table herebelow.
If a floor of this type is not available on site, fastening points of the specified concrete quality are acceptable.
The surface, on which the universal tyre-changer is to be installed, must be flat and well levelled in all directions.
Inclinations up to 0,25% relative to the horizontal can be compensated using suitable shims, wedges or the alike.
By means of a Widia bit Ø 16, drill a 0,63 inch (130 mm) into the floor passing through the holes provided on the base frame.
If there is an additional floor covering (B), or if shims or wedges are necessary for levelling (C), longer anchor bolts must be used.
Place an anchor bolt into each hole.
Make sure the anchor bolts extend at least 4.9” (125 mm.) into the concrete slab, as indicated in the drawing.
Tighten the anchor bolts fully.
When working with tire assembly, whose weight is higher than 2,204 lbs (1000 kg.), it is necessary to
fasten the tire-changer to the floor by means of proper anchor bolts.
Ground
Reinforced concrete
Electrowelded grid
Pebble gravel
B/5
98.4 inches (2,500 mm)
98.4 inches
(2,500 mm)
27.5 inches (700 mm)
39.3 inches
(1,000 mm)
Foundationsdimensions inch (cm).
Concrete
quality
Min. pressure
resistence
Length
Width
Thickness
B25
937 lbs/sqft
(425 Kg / cm
2
)
78,74
(200)
64,5
(164)
5,9
(15)
,9
1,96
5,90
,9
3,93
inches
ø 0,31
inches
Ø 0,7
Ø 0,7
Ø 0,7
MAX 0,25%
,9
,9
,9