Installation Guide_PV-ezRack_SolarTerraceII-A_AU_V2.0
1/10 Duerdin Street, Clayton VIC 3168 Australia
Tel: +61 3 9239 8088 Fax: +61 3 9239 8024
E-mail: [email protected] www.clenergy.com.au
20
page
of 21
Installation Instruction
5.8.3 Apply one pre-assembled Grounding Lug per T Rail. Click the Grounding Lug into to the channel
of T Rail, insert the Copper Wire (the maximum size is 6AWG or similar) and fasten the bolt M6*14 with
10N·m and fasten the bolt M8*25 with 13.5N·m as shown in figure below .
Step 6 Repeat above steps to install all PV Modules. Visually check Universal Clamp and PV modules
are properly positioned and tightly fasten all Clamps.
The recommended torque for Universal Clamps in End Clamp position is 13~14N·m.
The recommended torque for Universal Clamps in Inter Clamp position is 18~20N·m.
5.8.4 Now the installation is complete as shown in figure below. Please recheck all Bolts and fasten
them tightly using the recommended torque.
Fig. 28
Fig. 29